Saturday, 11 April 2020

What is Discrete Manufacturing, REM and Demand Management?

1. What is Discrete Manufacturing?
2. What is REM?
3. What is Demand Management?
Here are difference between Discrete and REM and small explanation about discrete and repetative manf.:
- A typical characteristic of discrete manufacturing is the frequent switching from one manufactured product to another. The products are typically manufactured in individually defined lots, the sequence of work centers through production varying for each one of these. Costs are calculated on the basis of orders and individual lots.
- In Repetitive Manufacturing, products remain unchanged over a longer period and are not manufactured in individually defined lots. Instead, a total quantity is produced over a certain period at a certain rate.
- Discrete manufacturing typically involves varying the sequence of work centers through which the products can pass during production. The order of work centers is determined in routings, which can often be very complex. There can be waiting times between the individual work centers. Also, semi-finished products are frequently placed in interim storage prior to further processing.
- Repetitive Manufacturing, on the other hand, normally involves a relatively constant flow on production lines. Semi-finished products are usually processed further immediately without being put in interim storage. Routings tend to be relatively simple.
- In discrete manufacturing, component materials are staged with specific reference to the individual production lots. Completion confirmations for the various steps and processes document the work progress and enable fine-tune controlling.
- In Repetitive Manufacturing, components are often staged at the production line without reference to a particular order. Completion confirmations are less detailed, and the recording of actual data is simplified.
- The function of Demand Management is to determine requirement quantities and delivery dates for finished products assemblies. Customer requirements are created in sales order management. To create a demand program, Demand Management uses planned independent requirements and customer requirements.
To create the demand program, you must define the planning strategy for a product. Planning strategies represent the methods of production for planning and manufacturing or procuring a product.
Using these strategies, you can decide if production is triggered by sales orders (make-to-order production), or if it is not triggered by sales orders (make-to-stock production).You can have sales orders and stock orders in the demand program. If the production time is long in relation to the standard market delivery time, you can produce the product or certain assemblies before there are sales orders. In this case, sales quantities are planned, for example, with the aid of a sales forecast.

The Difference Between MRP And MPS

The Difference Between MRP And MPS  


I was recently asked to discuss the difference between MRP and MPS. After providing the explanation, I thought it would be helpful information to share in a blog:
MPS stands for Master Production Schedule. A Master Production Schedule is the virtually exact same thing as MRP (Material Requirements Planning), the calculations are exactly the same, but there is one distinction.
MPS plans items that have “direct” demand, called independent demand. Independent Demand means that its demand comes from Sales Orders, Service Orders, or forecasts. The demand is directly from the customer requirements (or forecasted requirements).
MRP plans items that have “dependent” demand, demand that is passed down because of the need to produce an item.
So, if I make a pen, it has a cap, a barrel, a spring. and a refill. Based on the definition above, the pen is an MPS item. The cap, barrel, spring and refill are MRP items.
I will use my previous life in planning as the example:
When producing pens, we would lay out an MPS production plan on a weekly basis. That finished good production plan would be based on the orders and forecast for that period. That would create a “Finished Good” plan which would not be changed (well, we tried not to change it). This plan was important because we needed to manage the production plan to group items together by color to minimize molding change over time. This level loaded our production plan for the week and created the demand required for the components to produce that finished good plan. MRP would be run daily to expedite any parts required to produce the plan.
So, why would a company run MPS separate from their MRP items? Many times the finished good plan is going to be laid out and not changed. So rather than run MPS items daily and deal with the change requests (every day, new orders come in and change the requirements; therefore, you get messages that need to be dealt with). This is particularly true of companies that need to plan like items together.
I can think of two companies I have worked with in my consulting time that I suggested MPS planning. Both had finished good planning requirements similar to what I described above. They had a need to minimize change over time from one item to another. They also needed to set a schedule and produce to it. By running MPS separately, the schedule could be run once a week, and then MRP could be run more frequently to get action messages required to produce and maintain the production schedule.
If you have any further questions about MRP, MPS, or other manufacturing topics, please contact the manufacturing experts at ArcherPoint.

SAP Consumption-based Planning (CBP)

SAP Consumption-based Planning (CBP)

As the name indicates, this planning would be carried out based on the consumption values. The consumption values are the past historical consumption data. This data would then be used to calculate future requirements with the help of a forecasting program. For example, the requirements could be triggered when the material stock level falls below a reorder point. The reorder point would be calculated based on the past historical consumption data. There is another stock known as safety stock level. The safety stock should be maintained for the respective material to plan for the requirements and also for any unplanned delivery or any unexpected delay in supply from vendors.

What is MTS and MTO and the difference between them?


The difference between MTO and MTS is
MTO--> Make to Order
Production is the process where the production order is triggered from a Sales Order. Ex: The Prod process will start only after receiving the sales order from the customer. In this case the product could be customer specific only (Variant)
MTS--> Make to Stock
MTS scenario can be accomplished by the following settings
Need to use strategy group 20 in material master MRP view-Stretgy group 20 is assigned to strategy 20
Strategy 20 is assigned to Requirement type KE (Individual customer requirement)
Requirement type KE is assigned to requirement class 040 (Indiv.cust.w/o cons.)
Requirement class has all the parameters where we can define Prodcution order type that will be used to create the prod order. The above link needs to be established.
Also the MTS can be achieved using Sales Order schedule line catagory which will be assigned to Requirement type/class. Item category is assigned to Reqtype/class and the Item category is maintained in the material master.
You can use any of the baove config settings.
For MTO --> you just need to have all PP cycle settings in place nothing special needed as it is a plain PP cycle.
1. Make-to-order production is a process in which a product is individually manufactured for a particular customer. In contrast to mass production for an unspecified market where a material is manufactured many times, in make-to-order production a material is created only once though the same or a similar production process might be repeated at a later time.
2. You can use make-to-order production in two scenarios -
(a) For branches of industry or products where a small quantity of products with a large number of different characteristics are manufactured (Variant Configuration).
(b) When a product has to be assembled particularly for a sales order (Individual Customer Requirement).
3. Stock keeping is not usually carried out for products that are made to order. In companies using make-to-order production, the demand program only determines the production area, in which various variant types are produced. Depending on how you track the costs associated with make-to-order production, there are two ways to process make-to-order items during sales order processing.
(a) Make to order using sales order
(b) Make to order using project system (not relevant for SD application)
4. For make to order production using the sales order, all costs and revenues involved for an order item are held collectively at that item. A particular rule is used that can be changed manually to transfer costs to profitability analysis.
5. Make to order production is largely a production planning configuration. It is also controlled by the requirements type, which is determined by three things
the strategy group (MRP 3) in MMR
the MRP group (MRP1) in MMR
the item category and MRP type (MRP 1)
6. Make-to-order production is controlled by the requirements type. The requirements type is determined on the basis of the MRP group (MRP1) and the strategy group (MRP3) in the material master record. In addition, a plant must be assigned for make-to-order items in the sales order.

MTO - Make to Order
Make-to-order production with capacity checking enables vendors to trigger production of a requested product as soon as a sales order reaches the system. An automatic process checks machine capacity, schedules production, and determines the requested product’s availability date. This enables vendors to make immediate, reliable offers and commitments to their customers for the requested quantities and delivery dates. While particularly well-suited to high-tech manufacturers and makers of industrial machinery and equipment, this method also addresses the requirements of other make-to-order manufacturers.
MTS - Make to Stock
Make-to-stock production is designed for manufacturers that usually operate on the make-to-order model – configuring their finished goods after sales order entry – but that nevertheless manufacture the components of the finished goods in a make-to-stock process. The SAP best practice definition describes how manufacturers can accurately predict the future demand for components, communicate with suppliers of critical parts, and plan the production and distribution of finished goods, all based on actual material and capacity restrictions.

Friday, 10 April 2020

Maintain the Exchange Rate Type for version 000 in 20XX?

How to maintain Maintain the exchange rate type for version 000 in 2009?


1. Goto T-code 'okeq'.

2. On this page, select the line with version '0'. Further, click on Controlling area settings >> Settings for Each Fiscal Year.

3. System will pop-up a window asking you for controlling area, provide the same and click Enter.

4. It'll show Change View "Settings for Each Fiscal Year" : Overview page, under which select any year and copy as..(F6), change the year mentioned under it to subsequent year till 2009 and 'Save'. Ex: if last year mentioned is 2006, change the year to 2007 and save. Then, copy and change to 2008 and save. Lastly, carry out same operation for 2009 and save.

5. The exchange rate has now been set for year 2009.

You can carry out confirmation of production order now.

Friday, 27 March 2020

SAP PP TCODE With Description


C201                                      
Create Master Recipe
This transaction is used to create a master recipe for a finished or semi-finished material. The material, plant, version, and profile should be added on the initial screen. On the Recipe screen, the resource and the control should be added. On the Operations screen, the operation, description and the duration should be entered and these should be repeated for each phase of the operation.

C202
Change Master Recipe
This transaction is used to change a master recipe for a finished or semi-finished material. On the initial screen, the user should enter the recipe group. The transaction will display the Operations screen where the user can change the existing operation or add additional operations.

C203
Display Master Recipe
This transaction is used to display a master recipe for a finished or semi-finished material. On the initial screen, the user should enter the recipe group. The transaction will display the operations screen, where the user can review the operations. The user can review the materials in the recipe by clicking on the Materials tab. Recipe header information and administrative data can also be reviewed.

C223
Production Version: Mass Processing
This transaction is used to modify production versions based on certain selection criteria. The initial selection screen requires the user to enter a plant, but other selection criteria can be entered, such as material, MRP controller, key date, or production line. The transaction then will display the production versions, and the user can modify data for each, such as text, validity dates, lot size, planning group, production line, receiving storage location, and issuing location

C251
Master Recipe Print List
This transaction is used to print master recipes. The selection screen allows the user to enter a material, plant, recipe group, key date, planner group, recipe status, and usage. From the selection screen, the output shows all the relevant recipes based on the selection criteria. Each recipe shows the operation details, including the resource and activity types.

C252
Print List for Production Versions with Consistency Check
This transaction is used to print the details of a production version for a material. The selection screen allows the user to enter a material, plant, production version, task list type and type list group. The transaction output shows the production versions for each material, including the detailed planning and bill of materials information. The output will also display warning or error messages if there is an discrepancy with a production version.

C260
Task List Changes
This transaction displays any changes that have been made to a task list. The initial screen allows the user to enter a material, plant, recipe group, and a date range. The output shows the changes per object, which can include the item, the date change, and the user who made the change.

C261
Display Change Documents for a Recipe Group
This transaction displays the changes made to a recipe group. The initial screen allows the user to enter the recipe group, a date range for changes to be displayed, and the user who made the change. The output shows the date and time a change was made, the user who made the change, and the transaction used to make the change.

C298
Deletion of Task Lists without Archiving
This transaction is used to delete task lists but without archiving. The initial selection screen allows the user to enter a material, plant, group, status, task list usage or planner group. The transaction will propose a number of relevant task lists from which the user can deselect those that do not need to be deleted.

CA01
Create Routing
This transaction is used to create a routing, which is a description of which operations have to be carried out, and in what order, to produce a material. On the initial screen, the user needs to add a material and plant. On the next screen, the user needs to enter a value for the usage and a status. Operations can be added to the routing, including the work center, control key and description.

CA02
Change Routing
This transaction is used to change an existing routing. The initial screen requires a material and plant to be entered or a group number. The Operation Overview screen is displayed, where the user can add new operations or change existing ones.

CA03
Display Routing
This transaction is used to display an existing routing. The initial screen requires a material and plant to be entered or a group number. The transaction displays all the operations for the routing. The user can review other aspects of the routing, such as production resource/tool and inspection characteristics.

CA10
Standard Text
This transaction is used to create, change or display standard texts. The initial screen allows the user to enter a new standard text by entering a standard text key and a description. The next screen gives the user the option of entering a full screen of free-format text. If a standard text exists, then the screen will show the existing text, which can be changed.

CA11
Create Reference Operation Set
This transaction is used to create a reference operation set. The initial screen does not require a group number to be entered. The Header Details screen requires the user to enter the task list usage and the status key. Operations can be added with on the Operation Overview screen. Inspection characteristics can be entered for each operation.

CA12
Change Reference Operation Set
This transaction allows the user to change an existing reference operation set. The initial screen requires the user to enter a group number. The Operation Overview screen allows the user to enter a new operation or change an existing one. For each operation, the inspection characteristics can be changed or added.

CA13
Display Reference Operation Set
This transaction is used to display an existing reference operation set. The initial screen requires the user enter a group number. The transaction shows the operations associated with the group number. The user can review other aspects of the routing, such as production resource/tool and inspection characteristics.

CA21
Create Rate Routing
This transaction is used to create a rate routing, which is used when you plan on a quantity basis, for example in repetitive manufacturing. The initial screen does not require a group number to be entered. The Header Details screen requires the user to enter the task list usage and the status key. Operations can be added on the Operation Overview screen. Inspection characteristics can be entered for each operation.

CA22
Change Rate Routing
This transaction allows the user to change an existing rate routing. The initial screen requires the user to enter a group number. The Operation Overview screen allows the user to enter a new operation or change an existing one. For each operation, the inspection characteristics can be changed or added.

CA23
Display Rate Routing
This transaction is used to display an existing rate routing. The initial screen requires the user to enter a group number. The transaction shows the operations associated with the group number. The user can review other aspects of the routing, such as production resource/tool and inspection characteristics.

CA31
Create Reference Rate Routing
This transaction is used to create a reference rate routing, which is used when you plan on a quantity basis, for example in repetitive manufacturing. The initial screen does not require a group number to be entered. The Header Details screen requires the user to enter the task list usage and the status key. Operations can be added with on the Operation Overview screen. Inspection characteristics can be entered for each operation.

CA32
Change Reference Rate Routing
This transaction allows the user to change an existing reference rate routing. The initial screen requires a group number to be entered. The Operation Overview screen allows the user to enter a new operation or change an existing one. For each operation, the inspection characteristics can be changed or added.

CA33
Display Reference Rate Routing
This transaction is used to display an existing reference rate routing. The initial screen requires the user to enter a group number. The transaction shows the operations associated with the group number. The user can review other aspects of the routing, such as production resource/tool and inspection characteristics.

CA60
Task List Changes
This transaction is used to display the changes made to a task list. The initial screen requires the recipe group to be entered. The output screen shows each change by object, item, validity date, and the user who made the change.

CA62
Display Change Documents for Reference Operation Set Group
This transaction is used to display the changes for a reference operation set group. The initial screen requires a reference operation set group to be entered as well as an optional date range. The output screen shows each change to the reference operation set group. The details of each change are shown, including the change date and time, the user who made the change, and the date the change is valid from.

CA63
Display Change Documents for a Rate Routing
This transaction is used to display the changes for a rate routing. The initial screen requires a rate routing to be entered as well as an optional date range. The output screen shows each change to the rate routing. The details of each change are shown, including the change date and time, the user who made the change, and the date the change is valid from.

CA64
Display Change Documents for a Reference Rate Routing Group
This transaction is used to display the changes for a reference rate routing. The initial screen requires a reference rate routing to be entered as well as an optional date range. The output screen shows each change to the reference rate routing. The details of each change are shown, including the change date and time, the user who made the change, and the date the change is valid from.

CA70
Use of PRT in Task Lists
This transaction is used to find which task lists a production/resource tool is used in. On the initial screen, the user will need to enter the PRT material number, the plant number, and which task list types should be searched. The user can enter other optional search criteria to restrict the output, such as status, usage, and planner group.

CA75
Replace PRT in Task Lists
This transaction is used to make a mass change of a production resource/tool in selected task lists. On the initial screen, the user will need to enter the PRT material number, the plant number, and which task list types should be searched. The user can enter other optional search criteria to restrict the output, such as status, change number, usage, and planner group.

CA75N
Mass Change of PRT
This transaction is used to make a mass change of a production resource/tool in selected task lists. The user can enter the information on four screens. The initial screen allows the user to enter the material and plant. The second tab is for the task list screen, where the user can enter the task list or the task list types to be searched. The third tab is where the user can enter the new values, such as the material number. The final tab gives the user the option to delete multiple entries.

CA80
Work Center Where-Used
This transaction is used to display the task lists in which a specific work center is used. The initial screen requires the user to enter a work center, plant, and the task list types to be searched. The user can optionally enter other search criteria, such as status, usage, and planner group. The resulting display shows the task lists in which the work center is used in material order. The details displayed include the task list usage, validity dates, and control key.

CA81
Resource Where-Used
This transaction is used to display the task lists in which a specific resource is used. The initial screen requires the user to enter a resource, plant, and the task list types to be searched. The user can optionally enter other search criteria, such as status, usage, and planner group. The resulting display shows the task lists in which the resource is used in material order.

CA85
Replace Work Center
This transaction is used when a work center needs to be replaced in a selection of task lists. The initial screen requires the old and the new work center to be entered as well as the task list type. The user can optionally enter other search criteria, such as status, usage, and planner group. The resulting display shows the task lists in which the old work center is used, and the user can select the task lists in which the old work center needs to be replaced.

CA85N
Mass Change Work Center
This transaction allows the user to perform a mass change of work centers. The initial screen allows the user to enter a number of fields, such as material, plant, task list type, and planner group. The next screen gives the user the option to enter the new values for the work center and other data, such as control key, standard text key, and wage group.

CA87
Replace Work Center
This transaction is used when a work center needs to be replaced in a selection of task lists. The initial screen requires the old and the new work center to be entered as well as the task list type. The user can optionally enter other search criteria, such as status, usage, and planner group. The resulting display shows the task lists in which the old work center is used; the user can select the task lists in which the old work center needs to be replaced.

CA90
Use of Reference Operation Set in Task Lists
This transaction is used to find which task lists use a particular reference operation. On the initial screen the user will need to enter the group number, group counter, and which task list types should be searched. The user can enter other optional search criteria to restrict the output, such as status, usage, and planner group.

CA95                                                              
Replace Reference Operation Set
This transaction allows a user to replace a reference operation with a new reference operation. The initial screen requires the user to enter the old reference operation, the new reference operation, and the operation increment. The user can optionally enter other search criteria, such as status, usage, and planner group. The resulting display shows the task lists in which the old reference operation is used; the user can select the task lists in which the old reference option needs to be replaced.

CA95N
Mass Change Ref. Operation Set Reference
This transaction allows a user to replace a reference operation with a new reference operation. The initial screen requires the user to enter the old reference operation, the new reference operation. The next screen provides the user the opportunity to enter the task list type, status, usage, plant, and planner group. The final screen gives the user the option to delete multiple entries.

CA96
Update Material Master with Scheduling Results
This transaction is used to transfer scheduling results to a material master record. The initial screen requires the user to enter a plant and the production scheduler. The next screen displays the scheduling results for materials that can be updated. The set-up time, processing time, interoperation time, and assembly scrap can be updated in the material master record.

CA97
Update Material Master with Scheduling Results
This transaction is used to transfer scheduling results to a material master record. The initial screen requires the user to enter a single or range of material numbers, a plant, and a production scheduler. The user can select to have the material master records updated directly, updated with assembly scrap, or have the transaction carry out a CAPP calculation.

CA98
Deletion of Task Lists without Archiving
This transaction allows the user to delete task lists for a material. The initial screen requires the user to enter a material number, plant, and task list type. When executed, the transaction will delete the relevant task lists for the material, but there is no archiving of task lists, unlike transaction CA99.

CC01
Create a Change Master
This transaction is used to create a change master record. The initial screen allows the user to enter whether the change is a change master or an engineering change record. The following screen requires the user to enter a description for the change master record, a date from when the change is valid, and a status for the change master. The next screen gives the user the ability to determine which objects are valid for the change master, such as material, task list, or bill of materials.

CC02
Change a Change Master
This transaction is used to change a change master record. The initial screen requires the user to enter a change number. The following screen allows the user to change the validity date, authorization group and the reason for the change.

CC03
Display a Change Master
This transaction is used to display a change master record. The initial screen requires the user to enter a change number. The next screen will display the details of the change record, such as description, validity date, authorization group, status, and the reason for the change.

CC04
Product Structure Browser This transaction is used to display the details for the product. The initial screen has a number of tabs from which the user can choose. These tabs are for the material, document, change number, characteristic, class, equipment, and functional location. The user can enter information into one of the screens and the output will show the structure. For example, if a material is entered, the output will show a where-used list including the bill of materials it can be found within.

CC05
Change Overview
This transaction is used to display details relating to the change number. The initial screen has no mandatory selection fields, but the user can enter a change number, validity date, status, or a change type. The output shows the objects that have been affected by the individual change number. The output is shown in change number order.

CC07
Change Number Selection                                                                                                              
This transaction is used to display the details of a change number. The initial screen allows the user to enter a single or range of change numbers, as well as other selection criteria, such as validity date, and the user who created the change. The output screen shows the change number from which you can drill down to materials, bills of materials, or routings, where it was used.

CK11N
Create Material Cost Estimate with Quantity Structure
This transaction is used to create a material cost estimate. The initial screen requires the user to enter the material, plant number, and the costing variant. The next screen allows the user to enter the to and from dates for the validity of the cost estimate as well as the quantity structure date and the validation date. The transaction then shows the costing structure and the costs for each element in the structure.

CK13N
Display Material Cost Estimate with Quantity Structure
This transaction is used to display the material cost estimates for a material at a specific plant. The initial screen requires the user to enter a material, plant and a costing variant. The subsequent screen shows the costing structure and the costs for each element in the structure.

CK24
Price Update: Mark Standard Price
This transaction is used to update the standard price of materials. The initial screen requires the user to enter a posting period and fiscal year for the price update. The user can enter a specific company code, plant or material. There is also the option to flag the transaction so that the transaction will be run in test run mode only. The output screen of this transaction shows the future planned price for each material selected.

CK31
Print Error Log for Costing Run
This transaction is used to print any error log for a specific costing run. The initial screen requires the user to enter a costing run along with the relevant costing run date. The user can indicate which log he or she wants to print, such as the log for selection, costing, marking, release, or structure explosion. The transaction requires a printer to be entered, and the result is sent to the spool queue. The output will show the information, warning, and error logs for the costing run.

CK33
Comparison of Itemizations
This transaction is used to compare two costing estimates. The initial screen allows the user to enter the details of the two cost estimates, such as material, plant, costing variant, costing version and date. After the two cost estimates are entered, the transaction shows the details of the two cost estimates with differences shown as an absolute value or a percentage.

CK40N
Edit Costing Run
This transaction is used to edit an existing costing run. The initial screen requires the user to enter a costing run. The transaction allows the user to create a cost estimate for the selection, as well as a structure explosion, costing, analysis of material cost estimates, marking and release.

CK41
Create Costing Run (Material)
This transaction is used to create a costing run. The initial screen requires the user to enter a title for the costing run and a costing run date. The next screen requires a description to be added as well as a costing variant and a company code. The update parameters and print parameters need to be completed before the transaction is executed.

CK42
Change Costing Run (Material)
This transaction is used to change a costing run. The initial screen requires the user to enter the costing run and a costing run date. On the subsequent screen, the user can change the costing variant, controlling area, and the company code. The print parameters can also be changed so that the user can select which costing report to print.

CK43
Display Costing Run (Material)
This transaction is used to display a costing run. The initial screen requires the user to enter a costing run and the costing run date. The next screen shows the general data for the costing run, such as the costing variant, costing version, transfer control, and company code. The user can select to display the update parameters and the print parameters.

CK44
Delete Costing Run
This transaction is used to delete a costing run. The initial screen requires the user to enter a costing run and the costing run date. The other option the user has on the initial screen is to execute the transaction as a background job. When the transaction is executed, the details of the costing run are displayed. The user then has the option to confirm the deletion of the costing run.

CK80
Cost Component Report for Product Cost Estimate
This transaction shows the cost component report for a cost estimate. The initial screen requires the user to enter a material, plant and costing variant. The transaction displays the line item report for the material showing the overall, fixed and variable cost for each component.

CK82
List of Existing Material Cost Estimates
This transaction displays the cost estimates for a material. The initial screen requires the user to enter a plant, material, and costing variant. When the transaction is executed, the resulting screen shows details for the cost estimate, such as costing status, costing version, overall cost, and fixed cost.

CK84
Line Items in Cost Estimate for Product
This transaction shows the line items in the cost estimate for a material. The initial screen the user to enter a material, plant and costing variant. The output screen displays the line item report for the material showing the total and fixed value for each item.

CK85
Line Item Report Costing Items
This transaction is used to display the costing report for each item on a sales order. The initial screen requires the user to enter a sales order number. When the transaction is executed, the output screen displayed shows the line items relevant to the sales order. Each item shows the item category, resource, cost element, total value, fixed value and quantity.

CK86
Costed Multilevel BOM, Material Cost Estimate
This transaction shows the bill of materials hierarchy for the cost estimate for a material. The initial screen requires the user to enter a material, plant and costing variant. The next screen shows the hierarchy of the bill of materials explosion. The user can choose other options from the hierarchy screen, such as the cost component view or line items for the material view.

CK87
Costed Multilevel BOM, Sales Order Cost Estimate
This transaction shows the bill of materials hierarchy for the cost estimate for a sales order. The initial screen requires the user to enter a sales order number and the item number. The next screen shows the hierarchy of the bill of materials explosion. The user can choose other options from the hierarchy screen, such as the cost component view or line items for the material view.

CK88
Partner Cost Component Split
This transaction is used to produce a report that shows the partner component split. The initial screen requires the user to enter a plant, material and costing estimate. The user can enter a cost component view, such as for the cost of goods manufactured, cost of goods sold, inventory, etc.

CK89
Cost Component Report for Sales Document Cost Estimate
This transaction is used to display the cost component report for the sales document cost estimate. The initial screen allows the user to enter a sales order and a sales order item number. The line item report displays the cost components for the sales order. Each cost component shows the overall, fixed, and variable costs.

CK91
Create Procurement Alternative
This transaction is used to create a procurement alternative for a material. The initial screen requires a material and a plant to be entered. In addition, the initial screen allows the user to select a process category, such as production, purchase order, subcontracting, etc. The subsequent screen reflects the process category that was entered; the user needs to enter the specific information required.

CK91N
Display Procurement Alternatives
This transaction is used to display the procurement alternatives for a specific material at a plant. The initial screen requires a material and a plant to be entered. The resulting screen shows the procurement alternatives for the material and plant combination. The information can be seen by drilling down on the list of procurement alternatives.

CK92
Change Procurement Alternatives
This transaction is used to change procurement alternatives for a specific material at a plant. The initial screen requires a material and a plant to be entered. The subsequent screen shows the process categories for the material and plant combination. The user can select the appropriate process category and display the details to be changed.

CK93
Display Procurement Alternatives
This transaction is used to display the procurement alternatives for a specific material at a plant. The initial screen requires a material and a plant to be entered. The subsequent screen shows the process categories for the material and plant combination. The user can select the appropriate process category and display the details.

CK94
Change Mixing Ratios
This transaction is used to change the mixing ratios for procurement alternatives. The initial screen requires a material, plant, quantity structure type and fiscal year to be entered. The next screen shows the procurement alternatives and a mixing ratio can be entered for each. The mixing ratio is a weighting that is applied when the cost estimate of a procurement alternative is factored into the mixed cost estimate.

CK95
Display Mixing Ratios
This transaction is used to display the mixing ratios for procurement alternatives. The initial screen requires a material, plant, quantity structure type and fiscal year to be entered. The next screen shows the procurement alternatives and the mixing ratio for each.

CKC1
Check Costing Variant
This transaction is used to display the parameters that are linked to the costing variant and the assigned cost component layout. The initial screen requires the user to enter a costing variant, company code, and plant. The output shows a list of parameters for the costing variant, which allows you to check your settings for product costing.

CKR1
Reorganization of Cost Estimates
This transaction is used to reorganize the cost estimates for a company code, plant or material number. The initial screen allows the user to enter a company code, plant or material number. The user can also enter a control parameter and an option for processing. When executed, the transaction will display the cost estimates that have been reorganized.

CKW1
Create Cost Estimate for Production Lot
This transaction is used to create a cost estimate for a production lot. The initial screen requires the user to enter a costing variant, WBS element, material and plant. The next screen requires the user to enter the quantity structure date and a validation date. The transaction displays the costing data for the WBS element, and the cost estimate can then be saved.

CKW3
Display Cost Estimate for Production Lot
This transaction is used to display a cost estimate for a production lot. The initial screen requires the user to enter a costing variant, WBS element, material and plant. The next screen shows the costing estimate for the WBS element.

CKW4
Activate Cost Estimate for Production Lot
This transaction is used to activate a cost estimate for a production lot. The initial screen requires the user to enter a costing variant, WBS element, material and plant. The transaction will show a pop-up screen that asks whether the user wishes to activate the costing estimate. If the user selects Yes then cost estimate will be activated.

CM01
Capacity Planning: Selection (Work Center – Load)
This transaction is used for analysis purpose and capacity leveling. The initial screen allows the user to enter a work center and a plant number. The output display gives an overview of the available capacity, the capacity requirements for planned and production orders, and the capacity load in percentage for the next 60 working days summarized in a weekly format. If there is an overload, this is displayed with a red figure.

CM02
Capacity Planning: Selection (Orders)
This transaction is used for analysis purpose and capacity leveling. The initial screen requires a work center and plant to be entered. The output display shows the capacity details, which gives an overview of the planned and production orders that form the capacity requirement for the next 60 working days.

CM03
Capacity Planning: Selection (Work Center – Pool)
This transaction is used for analysis purposes and capacity leveling. The initial screen requires a work center and plant to be entered. The output will display an overview of the available capacity, the capacity requirements for released production orders, and the capacity load in percentage for the next 14 working days in a daily format. If there is an overload, this is displayed with a red figure.

CM04
Capacity Planning: Selection (Work Center – Backlog)
This transaction is used for analysis purposes and capacity leveling. The initial screen requires a work center and plant to be entered. The transaction output shows the capacity details, which gives an overview of the planned and production orders that should have been finished at least one day ago.

CM05
Capacity Planning: Selection (Work Center – Overload)
This transaction is used for analysis purpose and capacity leveling. The initial screen requires a work center and plant to be entered. The transaction shows an overview of the available capacity, the capacity requirements for planned and production orders, and the capacity load in percentage for the next 60 working days summarized in a weekly format. Only weeks with overload are displayed.

CM22
Capacity Leveling: SFC Planning Table
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter a work center, plant, capacity category, and a capacity planning group. On the output screen, which shows the period requirements per resource, the user can dispatch, dispatch manually, or deallocate.

CM23
Capacity Leveling: SFC Orders Tab
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter an order or a planned order. On the output screen, the user can dispatch, dispatch manually, or deallocate.

CM24
Capacity Leveling (Individual Capacity – Tabular)
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter a work center, plant, and capacity category. On the output screen, which shows the period requirements per resource, the user can dispatch, dispatch manually, or deallocate.

CM26
Capacity Leveling: Project View Tabular
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter a single or range of WBS elements. On the output screen, which shows the period requirements per resource, the user can dispatch, dispatch manually, or deallocate.

CM28
Capacity Leveling: SFC Individual Capacity Tab
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter a work center, plant, and capacity category. On the output screen, which shows the period requirements per resource, the user can dispatch, dispatch manually, or deallocate.

CM34
Capacity Leveling (Work Center – Tabular)
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter a work center and a plant. On the output screen, which shows the period requirements per resource, the user can dispatch, dispatch manually, or deallocate.

CM35
Capacity Leveling (Resource View – Table)
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter a work center, plant and capacity category. On the output screen, which shows the period requirements per resource, the user can dispatch, dispatch manually, or deallocate.

CM36
Capacity Leveling (Process Order View)
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter a single or range of orders and a single or range of planned orders. On the output screen, which shows the period requirements per resource, the user can dispatch, dispatch manually, or deallocate.

CM50
Capacity Leveling: SFC Work Center List
This transaction is used for capacity leveling, which overloads and underloads at work centers, achieving optimum commitment of machines and production lines, and selection of appropriate resources. The initial screen allows the user to enter a work center, plant and capacity category. The output screen shows the remaining capacity requirements per period, the available capacity per period, and the remaining available capacity for each work center.

CO01
Create a Production Order
This transaction is used to create a production order. The user is required to enter a material number and a plant. The user can enter an order type, such as a standard order, costing order or kanban order. The next screen requires a total quantity to be entered for the order as well as a start and end date for the order. The transaction will copy the BOM and routing into the order and then carry out the scheduling. The order can then be saved, causing the costs to be determined, and the transaction will finally display an order number.

CO01S
Create a Simulation Order
This transaction allows a user to create a simulation order. A simulation order enables a user to see how changes to initial data, e.g. a sales order, affect a production order. A user can use the simulation order to find errors in the material configuration. The simulation order is structured like a production order but has no effect on operations.

CO02
Change a Production Order
This transaction is used to change an existing production order. The initial screen requires the user to enter a production order. The next screen shows the header information with a number of tabs that can be selected to view other screens, such as Assignment, Control Data, Master Data and Administration. On the General screen, the user can change the order quantity, scrap portion, and the start and finish dates for the production order.

CO02S
Change a Simulation Order
This transaction allows a user to change an existing simulation order. A simulation order enables a user to see how changes to initial data, e.g. a sales order, affect a production order. A user can use the simulation order to find errors in the material configuration. The simulation order is structured like a production order but has no effect on operations. The user can change the same data that he or she would find in a production order, such as order quantity, and start and finish dates.

CO03
Display a Production Order
This transaction is used to display an existing production order. The initial screen requires the user to enter a production order. The user can then display details from any of the accessible screens, such as assignment, control data, master data and administration.

CO03S
Display a Simulation Order
This transaction allows a user to display an existing simulation order. A simulation order enables a user to see how changes to initial data, e.g. a sales order, affect a production order. A user can use the simulation order to find errors in the material configuration. The simulation order is structured like a production order but has no effect on operations. The user can display details from any of the accessible screens such as assignment, control data, master data and administration.

CO04
Print Shop Papers
This transaction gives the user the ability to print or reprint shop papers for orders at a specific plant. The initial screen requires the user to enter a plant number and choose whether the original print-out or a reprint is required. The user can enter other selection criteria such as MRP controller, production scheduler, order type, material or order number. The next screen shows a number of relevant production orders where the shop papers can be printed.

CO04N
Print Production Orders
This transaction gives the user the opportunity to print details for a single or range of production orders. The initial screen requires the user to enter at least one selection criterion, such as material, order type, MRP controller, sales order, WBS element or work center. The next screen shows a list of production orders that can be printed. The user can select the required orders and print the required document.

CO05N
Release Production Orders
This transaction is used to release production orders. The initial screen requires the user to enter at least one selection criterion, such as material, order type, MRP controller, sales order, WBS element or work center. The next screen shows a list of production orders that can be released. The user can select the relevant orders and the background processing will release the orders if there are no errors.

CO06
Backorder Processing
This transaction is used to perform backorder processing for a material. The initial screen requires a user to enter a material and a plant. The overview screen shows the available to promise (ATP) situation for the material at the plant. If necessary, the user can change the confirmation and reschedule.

CO07
Create a Production Order (Without Material)
This transaction is used to create a production order where no material number is entered. The initial screen requires the plant and order type to be entered. The user has the option to enter a sales order number, WBS element or a production order number. The next screen requires the user to enter a description for the material to be produced, the total quantity to be produced, the start and finish dates, and any scrap percentage. The transaction will return a production order number when processed.

CO08
Create a Production Order (For Sales Order)
This transaction is used to create a production order for a sales order. The initial screen requires the user to enter the sales order and sales order item number. The user can add other selection criteria, such as material, plant and order type. The next screen requires a total quantity to be entered for the order as well as a start and end date for the order. The transaction will copy the BOM and routing into the order and then carry out the scheduling. The order can then be saved, causing the costs to be determined, and the transaction will finally display an order number.

CO09
Availability Overview
This transaction is used to display an overview of the availability of a material. The initial screen requires the user to enter a material and a plant. The overview screen shows the available to promise (ATP) situation for the material at the plant. The transaction shows the MRP elements, such as production orders, purchase requirements, sales orders, etc.

CO10
Create a Production Order (For WBS Element)
This transaction creates a production order for a WBS element. The initial screen requires the user to enter a WBS element, a material number and a plant. The next screen requires a total quantity to be entered for the order as well as a start and end date for the order. The order can then be saved, causing the costs to be determined, and the transaction will finally display an order number.

CO11
Enter Production Order Confirmation
This transaction is used to enter the confirmation details for a production order. The initial screen requires the user to enter a confirmation number or an order number and operation. The next screen allows the user to enter the confirmation type and the confirmation details, such as yield, scrap and rework. The confirmation can then be saved, during which the costs are calculated.


CO11N
Enter Time Ticket for Production Order
This transaction allows the user to enter a time ticket for a production order. The initial screen requires the user to enter either a confirmation number or an order number and operation. In addition, the user can enter the confirmation details, such as yield, scrap and rework, in addition to the time spent on the activities performed during the operation.

CO12
Collective Entry: Time Ticket
This transaction is used to enter the time ticket information for a number of confirmations. The initial screen allows the user to enter the confirmation number, yield, scrap quantity, rework quantity, posting date, personnel number, work center, and the details for the activities.

CO13
Cancel Production Order Confirmation
This transaction is used to cancel a confirmation for a production order. The initial screen allows the user to enter a confirmation number or a production order and operation number. The user can enter the reason that the confirmation needs to be cancelled. After processing, the transaction will display a message indicating that the confirmation has been cancelled.

CO14
Display Production Order Confirmation
This transaction is used to display a production order confirmation. The initial screen allows the user to enter a confirmation number or a production order and operation number. The transaction will display the information entered for the confirmation such as yield, scrap and rework, in addition to the time spent on the activities performed during the operation.

CO15
Enter Production Order Confirmation
This transaction is used to enter the confirmation details for a production order. The initial screen requires a user to enter the relevant production order number. The next screen allows the user to enter the type of confirmation, the yield, confirmed scrap, rework, and the execution start and end date.

CO16N
Reprocessing Incorrect Confirmations
This transaction allows the user to reprocess incorrect confirmations for a production order. The initial screen allows the user to enter a production order number, a plant, confirmation number, WBS element, sales order, production scheduler or work center. The transaction will then reprocess the incorrect confirmations based on the selection criteria.

CO27
Picking List for Production Orders
This transaction can generate picking lists for a single or range of production orders. The initial screen allows the user to enter a number of selection criteria, including production order, material, plant, order type, MRP controller, sales order, WBS element, and work center. After the user has entered the selection criteria, the transaction will display a list of relevant production orders. The user can then select which orders should be picked.

CO40
Create a Production Order (Planned Order)
This transaction is used to create a production order from an existing planned order. The initial screen requires the user to enter a planned order number and an order type. The next screen allows the user to change the total quantity and the scrap percentage. After the user has entered any further information, the transaction can be saved and a production order number will be generated.

CO41
Collective Conversion of Planned Orders
This transaction is used to create production orders from a number of planned orders. The initial screen requires the user to enter a planning plant or production plant. The transaction will return a list of planned orders for the selection criteria that were entered. The user can select the relevant planned orders and then convert them to production orders.

CO43
Actual Overhead Calculation: Production/Process Orders
This transaction is used to calculate the actual overhead for production and process orders. The initial screen requires the user to enter a plant number, period, and fiscal year, and to select which types of orders are to be included, such as production orders, process orders and QM orders. The user can also select whether to run the transaction as a test run. The subsequent screen shows the processing details, such as number of orders for which the overhead was calculated, the number of orders that are not relevant, and the number of errors.

CO44
Mass Processing for Orders
This transaction is used to perform a processing on a number of orders. The transaction executes a number of functions for a range of process orders and production orders. The processing functions include scheduling, costing, capacity requirements, WM material staging, complete technically, and close the order. The user can enter a wide range of selection criteria, such as order type, plant, MRP controller, material number, order number, and sales order. The user can select which functions to process and can run the transaction in test mode if desired.

CO46
Order Progress Report: Selection Screen
This transaction is used to display the progress of a sales order, project, WBS element, production order, planned order or network. The initial screen has the option to enter a value for one of the choices, for example, a production order, and the transaction will display the progress of the order and show any exceptions that may have occurred, such as a delay because of a missing material.

CO48
Create a Production Order (Partial Conversion of Planned Order)
This transaction is used to create a production order by partially converting a planned order. The initial screen requires the user to enter a planned order number and an order type. The next screen allows the user to change the order quantity, along with the start and finish dates. Production order can then be generated and a production order number will be displayed.

CO78
Archiving of Production Orders
This transaction allows the user to archive production orders. The initial screen gives the user a selection so that he or she can set the deletion flag on orders, archive the orders, delete the orders and retrieve orders from archive. The user can set the deletion flag on a range of production orders by using a variant with the first option of this transaction.

CO88
Actual Settlement: Production/Process Orders
This transaction is used to perform the actual settlement for a range of production and process orders. The initial screen requires the user to enter a plant number, period, and fiscal year, and to select which types of orders are to be included, such as production orders, process orders and QM orders. The user can also select whether the transaction should be processed automatically or by period; in addition, the user can run the transaction as a test run. The subsequent screen shows the processing details, such as number of orders where the overhead was calculated, the number of orders that are not relevant, and the number of errors.

COB1
Create Batch Search Strategy
This transaction is used to create a batch search strategy. The initial screen requires the user to enter a strategy type, which controls the selection criteria, sort rule and the quantity proposal. The subsequent screen allows the user to enter validity dates for the strategy and then a number of materials can be added that will be relevant for the batch search strategy.

COB2
Change Batch Search Strategy
This transaction is used to change an existing batch search strategy. The initial screen requires the user to enter a strategy type, which controls the selection criteria, sort rule and the quantity proposal. The next screen allows the user to enter a single or range of materials can be changed. The subsequent screen shows the information for each material and the user can change the details, such as the number of batch splits, the quantity proposal, and the selection type.

COB3
Display Batch Search Strategy
This transaction is used to display an existing batch search strategy. The initial screen requires the user to enter a strategy type, which controls the selection criteria, sort rule and the quantity proposal. The next screen allows the user to enter a single or range of materials can be changed. The subsequent screen shows the information for each material and the user can review the details, such as the number of batch splits, the quantity proposal, and the selection type.

COFC
Reprocessing of Confirmations with Errors
This transaction is used to reprocess confirmations that have errors in the calculation of actual costs. The initial screen allows the user to enter a number of selection criteria to restrict the reprocessing; these include the order category, order number, confirmation number, and the date created. The subsequent screen shows the orders that have been found using the selection criteria. These orders can then be reviewed and reprocessed if appropriate.

COHV
Mass Processing Production Orders
This transaction allows the user to perform mass processing on a number of production orders. On the initial screen, the user can select the Mass Processing tab and choose which process to complete, such as confirmation, costing, release, scheduling, etc. The user can then access the selection screen and enter data into the selection criteria fields to choose the appropriate orders. The transaction will display the relevant orders. The user can select those orders that require the necessary processing.

COMAC
Collective Availability Check
This transaction allows the user to perform mass processing on a number of production orders for the material availability check. On the initial screen, the user can select the Mass Processing tab and choose which scope of processing is required, such as ATP check for all materials or individual checks. The user can then access the selection screen and enter data into the selection criteria fields to choose the appropriate orders. The transaction will display the relevant orders and the user can select the orders for which the availability check should be performed.

COOIS
Production Order Information System
This transaction allows the user to review information on a number of selected production orders. The initial screen requires the user to enter selection criteria to restrict the number of production orders to be reviewed. The subsequent screen shows the production orders relevant to the search. The user can then select the orders to be reviewed and then select to see the operation overview, component overview, status, configuration, stock/requirements list, and the stock overview.

COPD
Print Process Order
This transaction is used to print process orders. The initial screen gives the user a number of selection criteria to enter to restrict the number of process orders to select from. These criteria include the process order number, plant, production scheduler, MRP controller and order type. The transaction will display the orders based on the criteria and the user can select the relevant orders for printing.

COPI
Print Process Order Shop Floor Papers
This transaction gives the user the ability to print or reprint shop papers for orders at a specific plant. The initial screen requires the user to enter a plant number and to choose the original print-out or a reprint. The user can enter other selection criteria, such as MRP controller, production scheduler, order type, material or order number. The next screen shows a number of relevant production orders where the shop papers can be printed.

COR1
Create Process Order
This transaction is used to create a process order. The initial screen requires the user to enter a material number, a plant and an order type. The next screen requires the user to enter the total quantity of the process order, the start and finish dates, and the type of scheduling required, such as backwards or forwards scheduling. After processing, the transaction will display the process order number that has been generated.

COR2
Change Process Order
This transaction is used to change an existing process order. The initial screen requires the user to enter a process order number. The next screen is the General Data screen, on which the user can change the total quantity of the process order, the start and finish dates, and the type of scheduling required, such as backwards or forwards scheduling. The other screens that can be accessed are the Assignment, Goods Receipt, Control Data, and Master Data screens.

COR3
Display Process Order
This transaction is used to display a process order. The initial screen requires the user to enter a process order number. The next screen is the General Data screen, on which the user can display the total quantity of the process order, the start and finish dates, and the type of scheduling required, such as backwards or forwards scheduling. The other screens that can be displayed are the Assignment, Goods Receipt, Control Data, and Master Data screens.

COR5
Release Process Order
This transaction is used to release process orders that have been created. The initial screen requires the user to enter a plant; the user can also enter optional selection criteria, such as order type, MRP controller, production scheduler, process order number and release date. The transaction will show relevant process orders based on the selection criteria and the user can select the required process orders and release them. If there are any errors, the transaction will indicate that the release has been refused.

COR6
Create Process Order Confirmation
This transaction is used to confirm operations in a process order. The initial screen requires the user to enter a confirmation number or a process order number. The confirmation can be made for an operation in the process order.

COR6N
Enter Time Ticket for Process Order
This transaction allows the user to enter the time ticket information for a process order. The initial screen requires the user to enter a process order number or an order/sequence/operation combination. The user can choose between final and partial confirmation. The total yield and scrap can be entered for the process order.

COR7
Create Process Order from a Planned Order
This transaction allows the user to create a process order from an existing planned order. The initial screen requires the user to enter a planned order number and a process order type. The user has the ability to create a process order based on a partial conversion of the planned order. The next screen allows the user to change the total quantity, start and finish dates of the order, and the type of scheduling.

COR8
Collective Conversion of Planned Orders
This transaction is used to create process orders for a number of planned orders. The initial screen requires the entry of a plant, MRP area or planning plant. The next screen shows all of the planned orders for the selection criteria entered. The user can then select the required planned orders and convert them to process orders. The transaction will process the request, and any errors will be displayed.

CORA
Process Order: Scheduling External Relationships
This transaction is used to schedule external relationships for a process order. The initial screen requires the user to enter a process order. The next screen allows the user to change the start and finish dates of the process order.

CORK
Enter Process Order Confirmation
This transaction is used to enter a confirmation for a process order. The initial screen requires the user to enter the process order number. The next screen allows the yield to be entered as well as the personnel number, execution start and finish times, and any confirmation text.

CORO
Create Process Order without Material
This transaction is used to create a process order without a material number. The initial screen requires the user to enter a recipe group, recipe, plant number, and order type. The next screen shows the general data, where the user can enter the total quantity to be produced, as well as the start and finish dates for the order. Additional data can be entered before the process order is generated.

CORR
Collective Entry of Confirmations
This transaction is used to enter the information for a number of confirmations. The initial screen allows the user to enter the confirmation number, yield, scrap quantity, posting date, personnel number, and the details for the activities.

CORS
Cancel Process Order Confirmation
This transaction is used to cancel a confirmation for a process order. The initial screen allows the user to enter a confirmation number or a process order and operation number. The user can enter the reason that the confirmation is to be cancelled. After processing, the transaction will display a message indicating that the confirmation has been cancelled.

CORT
Display Process Order Confirmation
This transaction is used to display a process order confirmation. The initial screen allows the user to enter a confirmation number or a process order and operation number. The transaction will display the information entered for the confirmation, such as yield, scrap and rework, in addition to the time spent on the activities performed during the operation.

CORZ
Enter Confirmation of Process Order: Create Time Event
This transaction is used to enter a confirmation for a process order. The initial screen allows the user to enter a specific time event, such as start processing, processing partial finish, interrupt processing, or finish processing. The other information required on the initial screen is either a confirmation number or a process order number.

CR01
Create Work Center
This transaction is used to create a work center at a plant. The initial screen requires the user to enter a plant number, a work center category, and an eight-character work center number. The next screen requires a forty-character work center description, the responsible personnel, the location, task list usage, and rules for standard value maintenance, as it pertains to the set-up, machine and labor standard values. Other information, such as capacities, scheduling, and costing data, can be added before the work center is created.

CR02
Change Work Center
This transaction is used to change a work center at a plant. The initial screen requires a plant and work center to be entered. The next screen allows the user to change the work center description, the responsible personnel, the location, task list usage, and rules for standard value maintenance, as it pertains to the set-up, machine and labor standard values. Other information, such as capacities, scheduling, and costing data, can be changed.

CR03
Display Work Center
This transaction is used to display a work center at a plant. The initial screen requires a plant and work center to be entered. The user can then display information, including general data, default values, capacities, scheduling, costing, and technical data, on a number of screens.

CR05
Work Center List
This transaction is used to display a list of work centers based on the selection criteria entered. The initial screen does not require any mandatory entries, but the list of work centers can be reduced by entering selection criteria such as plant, work center, work center category, and person responsible. The resulting list will show the work centers based on the selection criteria. A work center can be selected and further details on that work center can be displayed.

CR06
Assignment of Work Centers to Cost Centers
This transaction is used to display which cost centers are assigned to a work center. The initial screen has no mandatory fields, but the output can be reduced by entering data into the selection criteria fields, which include the plant, work center, work center category, controlling area, and cost center. The resulting display shows the cost centers assigned to the work centers that are relevant to the search criteria.

CR07
Work Center Capacities
This transaction is used to display the capacity of a work center. The initial screen has no mandatory fields, but the output can be reduced by entering data into the selection criteria fields, which include the plant, work center, work center category, controlling area, and cost center. The resulting display shows work centers and the capacity categories for the work center. The user can select data on the output, such as work center, work center category, or the capacity category, to obtain further information.

CR08
Work Center Hierarchy
This transaction is used to view a work center hierarchy. The initial screen requires the user to enter a plant and hierarchy name. The resulting display shows the whole hierarchy, with the hierarchy level, work center, plant, work center category, and description. More information on each work center can be obtained by selecting a work center from the hierarchy list.

CR09
Standard Text
This transaction is used to create, change, delete, and display a standard text key. The initial screen requires the user enter a new standard text key if one is to be created, or an existing standard text key, if changes are to be made. If a new standard text key is entered, the transaction will display an empty screen where text can be entered. If the standard text key exists, the screen will display the existing text to be changed. The user also has the option to delete existing standard text keys.

CR10
Work Center Change Documents
This transaction is used to display work center change documents. The transaction will display change documents only if the configuration has been set to allow their creation for the work center category. In the initial screen, there are no mandatory fields, but the user can enter selection criteria data to restrict the number of change documents displayed, such as work center and work center category.

CR11
Create Capacity
This transaction is used to create capacity without assigning it to a work center. The initial screen requires the user to enter the plant where the capacity is to be assigned, the capacity category, such as labor or machine, and the name of the new capacity. The next screen provides the user the ability to enter a capacity planner group, factory calendar, start and finish time for the capacity and break times.

CR12
Change Capacity
This transaction is used to change existing capacity. The initial screen requires the user to enter a plant, capacity category and a capacity. The user can then change the capacity description, factory calendar, start and finish time for the capacity and break times.

CR13
Display Capacity
This transaction is used to display existing capacity. The initial screen requires the user to enter a plant, capacity category and a capacity. The user can then display the details of the capacity, such as the capacity description, factory calendar, start and finish time for the capacity and break times.

CR15
Capacity: Where Used
This transaction shows where a capacity has been used. The initial screen requires the user to enter a capacity name, although the user can enter other selection criteria, such as plant, category group, and planner group. The where-used list shows whether the capacity has been used as pooled capacity, basis for scheduling, or as reference available capacity.

CR21
Create Hierarchy
This transaction is used when a work center hierarchy is to be created. The initial screen requires the user to enter a ten-character hierarchy name and a plant number. The next screen requires a description for the hierarchy to be entered; the user can then assign work centers to the hierarchy. The user can assign the work centers to the hierarchy until the structure is complete.

CR22
Change Hierarchy
This transaction is used to change a work center hierarchy. The initial screen requires the user to enter a hierarchy name and a plant number. On the next screen, the user can change the hierarchy description. The user can then review the structure and add or change work center assignment as needed.

CR23
Display Hierarchy
This transaction allows a user to display a work center hierarchy. The initial screen requires a hierarchy name and a plant number to be entered. On the next screen, the user can display the hierarchy description. The user can then review the work center structure as a list or graphically.

CR60
Work Center Information System
This transaction displays the work center information system, which shows information on work centers. The initial screen has no mandatory fields, but there are number of selection criteria that will narrow the resulting display, such as capacity, hierarchies and cost centers. The output shows the work centers that are relevant for the selection criteria entered.

CS01
Create Material Bill of Material
This transaction is used to create a material bill of materials (BOM). The initial screen requires the user to enter a material number, plant number and a BOM usage key, which determines whether a BOM is used universally or just for production, plant maintenance, costing, etc. The next screen allows the user to enter the component materials and the quantities for the new BOM.

CS02
Change Material Bill of Material
This transaction is used to change a material bill of materials (BOM). The initial screen requires the user to enter a material number, plant number and a BOM usage key, which determines whether a BOM is used universally or just for production, plant maintenance, costing, etc. The next screen shows the component materials that have been assigned to the BOM. The user can add a new component material, change the values for an existing component, or delete a component material from the BOM.

CS03
Display Material Bill of Material
This transaction is used to display a material bill of materials (BOM). The initial screen requires the user to enter a material number, plant number and a BOM usage key. The next screen shows the component materials assigned to the material bill of materials.

CS05
Change Bill of Material Group
This transaction allows the user to change a bill of materials group, which is a material bill of materials that is not assigned to a plant. The initial screen requires a bill of materials group or a material/plant/BOM usage key to be entered. The next screen shows the assigned work centers, which can be changed as appropriate.

CS06
Display Bill of Material Group
This transaction allows the user to display a bill of materials group, which is a material bill of materials  that is not assigned to a plant. The initial screen requires a bill of materials group or a material/plant/BOM usage key to be entered. The next screen shows the work centers assigned to the bill of materials.

CS07
Create Plant Assignment
This transaction is used to assign a bill of materials group to a plant. The initial screen allows the user to enter a bill of materials group, BOM usage key, and a plant number to assign the BOM group to. On the next screen, the user can select the BOM and execute the transaction to assign it to the relevant plant.

CS08
Change Plant Assignment
This transaction is used to change the assignment of a bill of materials group to a plant. The initial screen allows the user to enter a bill of materials group, BOM usage key, and the plant number that the BOM group is assigned to. The user can delete an assignment to a plant if the bill of materials is no longer required at that facility.

CS09
Display Plant Assignment
This transaction is used to display the assignments for a bill of materials group. The initial screen allows the user to enter a bill of materials group, BOM usage key, and the plant number that the BOM group is assigned to. The next screen shows the allocations for the bill of materials.

CS11
Explode BOM: Level by Level
This transaction allows the user to explode a bill of materials to view the component materials level by level. The initial screen requires the user to enter the material, the plant number and the BOM application, such as plant maintenance, costing, rework, and production. The next screen displays the exploded bill of materials level by level.

CS12
Explode BOM: Multi-Level BOM
This transaction allows the user to explode a bill of materials to view the component materials on a multi-level basis. The initial screen requires the user to enter the material, the plant number and the BOM application, such as plant maintenance, costing, rework, and production. The next screen displays the exploded multi-level bill of materials.

CS13
Explode BOM: Summarized BOM
This transaction allows the user to explode a bill of materials to view a summarized display of the component materials. The initial screen requires the user to enter the material, the plant number and the BOM application, such as plant maintenance, costing, rework, and production. The next screen displays a summarized bill of materials.

CS14
Bill of Material Comparison
This transaction is used to compare two bills of materials and show the display as a summarized comparison, multi-level comparison, or a differentiated comparison. The initial screen requires the user to enter the details for the two bills of material, such as material, plant, BOM usage key. The output shows the differences between the two BOMs.

CS15
Material Where-Used List: Bill of Material
This transaction allows the user to investigate where a material is used, as it pertains to the bill of materials. The user can enter a material into the initial screen, in addition to the type of where-used list required and the type of BOMs to be reviewed. The resulting screen shows the entire bill of materials that the material is used in.

CS20
Mass Changes: Material BOM
This transaction is used to perform a mass change on work centers related to a specific material. The initial screen allows the user to enter a component material number and the user has to select whether the change is for existing item data, add a material, add a document, add a class, or delete an item.

CS21
Mass Changes: Material Selection
This transaction is used to perform a mass change on work centers related to a specific material. The initial screen allows the user to enter a component material number and the user has to select whether the change is for existing item data, add a material, add a document, add a class, or delete an item. This transaction is similar in processing to CS20.

CS22
Mass Changes: Document Selection
This transaction is used to perform a mass change on documents related to a specific document structure. The initial screen allows the user to enter a document number and the user has to select whether the change is for existing item data, add a material, add a document, add a class, or delete an item.

CS23
Mass Changes: Class Selection
This transaction is used to perform a mass change on a class related to a specific material BOM. The initial screen allows the user to enter a class number and the user has to select whether the change is for existing item data, add a material, add a document, add a class, or delete an item.

CS40
Creating Bill of Materials Configurable Link
This transaction is used to create a bill of materials configurable material link. On the initial screen, the user should enter the material, plant and the BOM usage key. On the next screen, the Current Assignments screen, the user selects the material and processed the transaction so that the bill of materials is assigned to the configurable material.

CS41
Change Bill of Materials Configurable Link
This transaction allows the user to delete the bill of materials configurable material link. On the initial screen, the user should enter the material, plant and the BOM usage key. On the next screen, the Current Assignments screen, the user chooses the option to delete and process the transaction so that the bill of materials is no longer assigned to the configurable material.

CS42
Display Bill of Materials Configurable Link
This transaction allows the user to display the bill of materials configurable material link. On the initial screen, the user should enter the material, plant and the BOM usage key.

CS51
Create Standard Bill of Material
This transaction is used to create a standard bill of materials. The initial screen requires a standard object, which does not have a material master record, and a BOM usage key. On the next screen, the user can enter a number of material components with the relevant quantities. After processing, the transaction will display a message indicating that the standard BOM has been created.

CS52
Change Standard BOM
This transaction is used to change a standard bill of materials. The initial screen requires a standard object, which does not have a material master record, and a BOM usage key. On the next screen, the user can enter additional material components with the relevant quantities, change existing components or delete existing components. After processing, the transaction ill display a message indicating that the standard BOM has been changed.

CS53
Display Standard BOM
This transaction is used to display a standard bill of materials. The initial screen requires a standard object, which does not have a material master record, and a BOM usage key. On the next screen, the user can review the contents of the standard bill of materials.

CS61
Create Order BOM
This transaction is used to create a bill of materials for a sales order. The initial screen requires the user to enter the sales order number, the sales order item number, the material number and the BOM usage key. The next screen allows the user to enter the component materials and quantities for the bill of materials. After processing, a message will be displayed indicating that a BOM has been created for a customer order.

CS62
Change Order BOM
This transaction is used to change a bill of materials for a sales order. The initial screen requires the user to enter the sales order number, the sales order item number, the material number and the BOM usage key. The next screen allows the user to enter additional component materials and quantities, edit existing components or delete existing components. After processing, a message will be displayed indicating that a BOM has been changed for the customer order.

CS63
Display Order BOM
This transaction is used to display a bill of materials for a sales order. The initial screen requires the user to enter the sales order number, the sales order item number, the material number and the BOM usage key. The next screen allows the user to review the components on the bill of materials for the customer order.

CS71
Create WBS BOM
This transaction is used to create a bill of materials for a WBS element. The initial screen requires the user to enter the WBS element number, material number, plant number, and the BOM usage key. The next screen allows the user to enter the component materials and quantities for the bill of materials. After processing, a message will be displayed indicating that a BOM has been created for the WBS element.
CS72
Change WBS BOM
This transaction is used to change a bill of materials for a WBS element. The initial screen requires the user to enter the WBS element number, the material number, plant number, and the BOM usage key. The next screen allows the user to enter additional component materials and quantities, edit existing components or delete existing components. After processing, a message will be displayed indicating that a BOM has been changed for the WBS element.

CS73
Display WBS BOM
This transaction is used to display a bill of materials for a WBS element. The initial screen requires the user to enter the WBS element, material number, plant number, and the BOM usage key. The next screen allows the user to review the components on the bill of materials for the WBS element.

CS80
Display Change Documents: Material BOM
This transaction is used to display change documents for a material bill of materials. The initial screen requires the user to enter a material number, plant number, and BOM usage key. The next screen gives the user the option to display a document overview or display the full document. The document overview shows the user the document number, date and object ID. The full document display shows all details from the change document.

CS81
Display Change Documents: Standard BOM
This transaction is used to display change documents for a standard bill of materials. The initial screen requires the user to enter a standard object and BOM usage key. The next screen gives the user the option to display a document overview or display the full document. The document overview shows the user the document number, date and object ID. The full document display shows all details from the change document.

CS82
Display Change Documents: Order BOM
This transaction is used to display change documents for a sales order bill of materials. The initial screen requires the user to enter the sales order, the sales order item number, the material number, and BOM usage key. The next screen gives the user the option to display a document overview or display the full document. The document overview shows the user the document number, date and object ID. The full document display shows all details from the change document.

CS83
Display Change Documents: WBS BOM
This transaction is used to display change documents for a WBS element bill of materials. The initial screen requires the user to enter the WBS element, the material number, the plantnumber, and BOM usage key. The next screen gives the user the option to display a document overview or display the full document. The document overview shows the user the document number, date and object ID. The full document display shows all details from the change document.

CSK1
Explode BOM: Level by Level
This transaction explodes the sales order bill of materials, level by level. The initial screen requires the user to enter the sales order number, sales order item number, material number, and application. The next screen displays the sales order bill of materials, level by level.

CSK2
Explode BOM: Multi-Level BOM
This transaction explodes the multi-level sales order bill of materials. The initial screen requires the user to enter the sales order number, sales order item number, material number, and application. The next screen displays the multi-level sales order bill of materials.

CSK3
Explode BOM: Summarized BOM
This transaction explodes the sales order bill of materials and displays it in a summarized mode. The initial screen requires the user to enter the sales order number, sales order item number, material number, and application. The next screen displays the summarized sales order bill of materials.

MB11
Enter Goods Movement
This transaction is used to enter a goods movement, specifically consumption for a cost center, receipt without a purchase order, or a transfer posting plant to plant. On the initial screen, the user needs to enter the movement type and plant number. The next screen requires the user to enter the material information and to process the goods movement.

MB31
Goods Receipt for Production Order
This transaction is used to enter a goods movement, specifically for the receipt of a production order. On the initial screen, the user needs to enter the movement type, which is 101, the production order number, and plant number. The next screen requires the user to enter the material quantity and to process the goods movement.

MBVR
Manage Reservations
This transaction is used to manage existing reservations and to delete those that are obsolete. The initial screen does not have any mandatory fields, but the user can enter data into the selection criteria, such as cost center, production order, project, sales order, etc., to reduce the list of reservations. The next screen shows the reservations that have been selected to be deleted. The user can select which reservations he or she wishes to delete and execute the transaction.

MC35
Create Rough-Cut Planning Profile
This transaction is used to create a rough-cut planning profile, which can be used to plan work center capacities, raw materials, costs, and production resources and tools. The initial screen requires the user to enter a product group with a plant, a material with a plant, or an information structure. If a material and plant are entered, a pop-up screen will show the general data, which will require some data to be entered such as status and usage. The next screen allows the user to enter resources and the quantity for the periods in the planning profile.

MC36
Change Rough-Cut Planning Profile
This transaction is used to change a rough-cut planning profile. The initial screen requires a user to enter a product group with a plant, a material with a plant, or an information structure. If a material and plant are entered, the planning profile will be displayed so that the user can change the values for the resources for the periods entered. Resources can be added or deleted in the planning profile.

MC37
Display Rough-Cut Planning Profile
This transaction is used to display a rough-cut planning profile. The initial screen requires the user to enter a product group with a plant, a material with a plant, or an information structure. If a material and plant are entered, the planning profile will be displayed so that the user can review the values for the resources for the periods entered.

MC61
Create Planning Hierarchy
This transaction is used to create a planning hierarchy, which represents the organizational levels and units in the company to be planned. A planning hierarchy is a combination of characteristic values based on the characteristics of one information structure, which the user enters on the initial screen. Depending on the information structure entered, a dialog box is displayed that requires the user to enter values for the characteristics from the information structure. After the characteristics are entered, the hierarchy can be saved.

MC62
Change Planning Hierarchy
This transaction is used to change a planning hierarchy, which represents the organizational levels and units in the company to be planned. A planning hierarchy is a combination of characteristic values based on the characteristics of one information structure. On the initial screen, the user is required to enter the information structure number. The subsequent screens reflect the information that was entered into the characteristics and this information can be changed using this transaction.

MC63
Display Planning Hierarchy
This transaction is used to display a planning hierarchy, which represents the organizational levels and units in the company to be planned. A planning hierarchy is a combination of characteristic values based on the characteristics of one information structure. On the initial screen, the user is required to enter the information structure number. The subsequent screens will display the information that was entered into the characteristics.

MC64
Create Event
This transaction is used to create an event, for example, a planned sales promotion that is entered to show the impact on the forecast. The initial screen can be left blank so the transaction displays an event number. The user can add an event description, status, event type, and event length. The user can then enter an absolute change that would be caused by the event. This change can then be assigned to a key figure in an information structure.

MC65
Change Event
This transaction is used to change an event, for example, a planned sales promotion that is entered to show the impact on the forecast. The initial screen requires the user to enter an event number. The next screen allows the user to change the values caused by the event, which can be assigned to a key figure in an information structure.

MC66
Display Event
This transaction is used to display an event, for example, a planned sales promotion that is entered to show the impact on the forecast. The initial screen requires the user to enter an event number. The next screen allows the user to display the values caused by the event, which have been assigned to a key figure in an information structure.

MC67
Planning Hierarchy Graphic
This transaction is used to display the planning hierarchy in a graphical form. The initial screen requires the user to enter the information structure. The transaction then displays a pop-up screen that offers the user a number of selection criteria. Based on the selection criteria, the transaction graphically displays the hierarchy.

MC71
Product Group Hierarchy
This transaction is used to display a product group hierarchy. The initial screen requires the user to enter a product group number, the relevant plant, and the display level, which can be a structural display or single-level display. The resulting output shows the product group in the format required, including the material number, plant and description. The user can then request additional information, such as unit conversion, version, material type, and proportion.

MC72
Product Group Usage
This transaction is used to display a product group usage. The initial screen requires the user to enter a product group number, the relevant plant, and the display level, which can be a structural display or single-level display. The resulting output shows the product group in the format required, including the material number, plant and description. The user can then request additional information, such as unit conversion, version, material type, and proportion.

MC73
Product Group Usage (Material)
This transaction is used to display a product group usage for a material. The initial screen requires the user to enter a material, the relevant plant and the display level, which can be a structural display or single-level display. The resulting output shows the material and the product group it is associated with in the format required, including the material number or product group, plant and description. The user can then request additional information, such as unit conversion, version, material type, and proportion.

MC74
Transfer Planning Data to Demand Management (Material)
This transaction is used to transfer planning data for a material to demand management. The initial screen requires the user to enter a material and plant. The user is also required to choose which transfer strategy to use, such as the sales plan or production plan. In addition, the user must enter the date period for the data that the user wishes to transfer to demand management.

MC75
Transfer Planning Data to Demand Management (Product Group)
This transaction is used to transfer planning data for a product group to demand management. The initial screen requires the user to enter a product group and plant. The user is also required to choose which transfer strategy to use, such as the sales plan or production plan. In addition the user must enter the date period for the data that the user wishes to transfer to demand management.

MC76
Change Plan
This transaction is used to change an existing active or inactive plan. The initial screen requires the user to enter the product group number and the plant number, and to choose an inactive or active plan. The transaction displays a screen where the user can choose to create a sales plan, disaggregate the production plan, disaggregate target stock, or disaggregate a sales plan.

MC77
Display Plan
This transaction is used to display an existing active or inactive plan. The initial screen requires the user to enter the product group number and the plant number, and to choose an inactive or active plant. The transaction displays a screen where the product group members are shown.

MC78
Copy Planning Version
This transaction is used to copy a planning version. The initial screen shows by default information structure S076, and requires the user to enter a source planning version and a target planning version with a description.

MC79
Change SOP: User Settings
This transaction is used to change SOP settings for a user. The initial screen shows the users, which can be changed. A user can be selected and then the settings, such as the planning start date and information structure, can be amended.

MC80
Delete Planning Version
This transaction is used to delete a planning version for information structure S076. The initial screen shows all the planning versions and the user can select a version or versions that the user wishes to delete.

MC81
Create Rough-Cut Plan
This transaction is used to create a rough-cut plan based on a product group and plant. The initial screen requires the user to enter the specific product group and associated plant number. The transaction displays a pop-up screen where the user can enter a version number and description. The next screen allows the user to enter values for each period of the plan, for sales, production, target stock level and target day’s supply.

MC82
Change Rough-Cut Plan
This transaction is used to change a rough-cut plan. The initial screen requires the user to enter the specific product group and associated plant number. The user can choose between the active version and inactive versions of the plan. Once a plan is selected, the user can change the values for each period of the plan, for sales, production, target stock level and target day’s supply.

MC83
Display Rough-Cut Plan
This transaction is used to display a rough-cut plan. The initial screen requires the user to enter the specific product group and associated plant number. The user can choose between the active version and inactive versions of the plan. Once a plan is selected, the user will be able to review the values in the rough-cut plan.

MC84
Create Product Group
This transaction is used to create a product group. The initial screen requires the user to enter a product group number, the plant where the product group will exist, and a unit of  measure that will be used for the items in the product group. On the next screen, the materials, or product groups, that will be part of the product group can be entered. An aggregation factor and the factor for disaggregation can be entered for each entry.

MC85
Display Product Group
This transaction is used to display a product group. The initial screen requires the user to enter a product group number and a plant. The next screen shows the details of the product group. Each product group member is displayed along with its associated aggregation factor and the factor for disaggregation.

MC86
Change Product Group
This transaction is used to change a product group. The initial screen requires the user to enter a product group number and a plant. The next screen shows the details of the product group. Each product group member is displayed and the user can change the values for the aggregation factor and the factor for disaggregation. Additional product group members can be added to the product group or the existing members can be deleted.

MC87
Create Rough-Cut Plan (Material)
This transaction is used to create a rough-cut plan based on a material and plant. The initial screen requires the user to enter the specific material and associated plant number. The transaction displays a pop-up screen where the user can enter a version number and description. The next screen allows the user to enter values for each period of the plan, for sales, production, target stock level and target day’s supply.

MC88
Change Rough-Cut Plan (Material)
This transaction is used to change a rough-cut plan. The initial screen requires the user to enter the specific material and associated plant number. The user can choose between the active version and inactive versions of the plan. Once a plan is selected, the user can change the values for each period of the plan, for sales, production, target stock level and target day’s supply.

MC89
Display Rough-Cut Plan (Material)
This transaction is used to display a rough-cut plan. The initial screen requires the user to enter the specific material and associated plant number. The user can choose between the active version and inactive versions of the plan. Once a plan is selected, the user will be able to review the values in the rough-cut plan.

MC8A
Planning Type: Create
This transaction is used to create a new planning type. The initial screen requires the user to enter a planning type number. The transaction requires the user to enter an information structure and will then display a screen to allow the entry of a description, single or dual level planning, planning horizon values and standard calculations.

MC8B
Planning Type: Change
This transaction is used to change a new planning type. The initial screen requires the user to enter an existing planning type number. The user can then add a new structure into the planning type, as well as an event and actual data.

MC8C
Planning Type: Display
This transaction is used to display a new planning type. The initial screen requires the user to enter an existing planning type number. The user can then review the aggregate information for the planning type.

MC8D
Create Planning Job
This transaction is used to create a planning job. The initial screen requires the user to enter a ten-character job number and a job name. The next screen requires the user to enter an information structure and a version number. A pop-up screen will be displayed showing the planning types; the user is required to select one. The next screen will display the relevant variants and the user one can select one.

MC8E
Change Planning Job
This transaction is used to change a planning job. The initial screen requires the user to enter a ten-character job number and a job name. The next screen will allow the user to enter characteristics for the variant. Once the fields in the variant have been entered, the variant can be saved.

MC8G
Schedule Background Run for Selected Planning Objects
This transaction is used to schedule background jobs for planning objects. The initial screen requires a job number to be entered. Once executed, the transaction will allow the user to enter information about when the job is to be run, such as immediately, or to schedule it for a later time.

MC8J
List of Planning Objects
This transaction is used to display a list of materials and product groups associated with a planning job. The initial screen requires the user to enter a job name. The output display shows a list of the materials and product groups associated with the planning job. The user can then select a material or product group and delete that object from the job, if required.

MC8V
Copy Planning Version
This transaction is used to copy a planning version. The initial screen shows by default information structure S076, and requires the user to enter a source planning version and a target planning version with a description.

MC8W
Delete Planning Version
This transaction is used to delete a planning version for information structure S076. The initial screen will show all the planning versions and the user can select a version or versions for deletion.

MC90
Transfer Planning Data to Demand Management
This transaction is used to transfer planning data for a material to demand management. The initial screen requires the user to enter a material, plant, information structure and version. The user is also required to enter the key figure from the information structure, along with a relevant date range.

MC91
Product Hierarchy Graphic
This transaction is used to display a product hierarchy in a graphical form. The initial screen requires the user to enter a product group and plant. The user can indicate that he or she requires the display to show descriptions and the materials to be displayed.

MC93
Create Rough-Cut Plan in Flexible Planning
This transaction is used to create a rough-cut plan in flexible planning. The initial screen requires the user to enter a planning type. The next screen requires a material and plant to be entered. A pop-up screen will appear so that the user can enter a version number. The detail screen shows the objects from the planning table and the user can enter values into the periods of the rough-cut plan for each object.

MC94
Change Rough-Cut Plan in Flexible Planning
This transaction is used to change a rough-cut plan in flexible planning. The initial screen requires a planning type to be entered. The next screen requires a material and plant to be entered as well as a choice of the active or inactive versions. The detail screen shows the objects from the planning table and the user can amend values into the periods of the rough cut plan for each object.

MC95
Display Rough-Cut Plan in Flexible Planning
This transaction is used to display a rough-cut plan in flexible planning. The initial screen requires a planning type to be entered. The next screen requires a material and plant to be entered as well as a choice of the active or inactive versions. The detail screen shows the objects from the planning table and the user can review the values into the periods of the rough-cut plan for each object.

MC9K
Maintain Available Capacity for Material
This transaction is used to amend the available capacity for a material. The initial screen requires the user to enter a material number, plant number and version number. The next screen allows the user to enter a number of period dates and the availability capacity value for each of the periods.

MCP1
Operation Analysis
This transaction is used to perform an analysis on operation data. The initial screen allows the user to enter a number of selection criteria, such as plant, material, work center, date range, and order. The resulting display is based on the selection criteria that the user entered. It shows the target lead time, which is the time period between the scheduled input date at the work center and the latest scheduled finish of the operation, and the actual lead time, which is the time between the input date at the work center and the completion confirmation date.

MCP3
Production Order Analysis
This transaction is used to perform an analysis on production order data. The initial screen allows the user to enter a plant, material and production order. The resulting display is based on the selection criteria that the user entered and shows the target lead time and actual lead time. The user can drill down on the results to find data on materials and order numbers.

MCP5
Material Analysis
This transaction is used to perform an analysis on material data. The initial screen allows the user to enter a plant, MRP controller and material. The resulting display is based on the selection criteria that the user entered and shows the target lead time and actual lead time. The user can drill down on the results to find data on MRP controller and materials.

MCP7
Work Center Analysis
This transaction is used to perform an analysis on work center data. The initial screen allows the user to enter a plant, planner group, and work center. The resulting display is based on the selection criteria that the user entered and shows the target lead time and actual lead time. The user can drill down on the results to find data on the planner groups.

MCRE
Material Usage Analysis
This transaction is used to perform an analysis on material usage data. The initial screen allows the user to enter a plant, material, bill of materials component, and production order. The resulting display is based on the selection criteria that the user entered and shows the target lead time and actual lead time. The user can drill down on the results to find data on the material, BOM component, and production order.

MCRI
Product Costs Analysis
This transaction is used to perform an analysis on product costing data. The initial screen allows the user to enter a plant, material, bill of materials component, costing activity type, and production order. The resulting display is based on the selection criteria that the user entered and shows the total value in the controlling area, fixed value in the controlling area, and the variable value in the controlling area. The user can drill down on the results to find data on the material, BOM component, and costing activity type.

MCRX
Material Usage Analysis
This transaction is used to perform an analysis on material usage data. The initial screen allows the user to enter a plant, material, bill of materials component, and production order. The resulting display is based on the selection criteria that the user entered and shows the requirement quantity and the withdrawal quantity. The user can drill down on the results to find data on the material, BOM component, and production order.

MCRY
Product Costs Analysis
This transaction is used to perform an analysis on product costing data. The initial screen allows the user to enter a plant, material, bill of materials component, costing activity type, and production order. The resulting display is based on the selection criteria that the user entered and shows the total value in the controlling area, fixed value in the controlling area, and the variable value in the controlling area. The user can drill down on the results to find data on the material, BOM component, and costing activity type.

MD01
MRP Run
This transaction is used to generate an MRP run. On the initial screen, the user can enter a scope of planning value, a plant number, processing key, creation indicator for purchase requisitions, automatic scheduling line indicator, planning mode value, and planning date. The resulting display shows details on the planning run, such as the number of materials planned and the number of any errors generated.

MD02
Single-Item, Multi-Level (MRP)
This transaction is used to perform a single item, multi-level MRP run. On the initial screen, the user can enter a material, MRP area, a plant number, processing key, creation indicator for purchase requisitions, automatic scheduling line indicator, planning mode value, and planning date. The resulting display shows details on the planning run, such as the number of materials planned and the number of any errors generated.

MD03
Single-Item, Single-Level (MRP)
This transaction is used to perform a single item, single-level MRP run. On the initial screen, the user can enter a material, MRP area, a plant number, processing key, creation indicator for purchase requisitions, automatic scheduling line indicator, planning mode value, and planning date. The user can also flag the indicator that displays the results before they are saved. If required, the resulting display shows the planning result for the individual lines.

MD05
MRP List (Individual Display)
This transaction is used to display the MRP list for an individual material. The initial screen allows the user to enter a material, MRP area, and a plant. The transaction will then show the MRP list for the material, showing each of the MRP elements such as purchase requisitions, safety stock, production orders, consignment material, etc.

MD06
MRP List (Collective Display)
This transaction is used to display the MRP list for an MRP area or plant. The initial screen allows the user to enter an MRP area or a plant. In addition, the user can enter an MRP controller, a product group or a vendor. The next screen shows a list of materials with MRP lists that can be selected, and the MRP list can be reviewed.

MD07
Stock/Requirements List (Collective Display)
This transaction is used to display a stock/requirements list for a number of materials. The initial screen allows the user to enter MRP area or a plant. In addition, the user can enter an MRP controller, a product group or a vendor. The next screen shows a list of materials with stock/requirements lists that can be selected, and an individual stock/requirements list can be reviewed.

MD08
Delete MRP Lists
This transaction is used to delete MRP lists. The initial screen allows the user to enter a plant, MRP area, MRP controller, or MRP date. The user can flag that the executed transaction be run in test mode. The next screen shows the MRP lists that can be deleted.

MD09
Determine Pegged Requirements
This transaction is used to determine the pegged requirements. The initial screen allows the user to enter one of the following: a planned order, production order, purchase requisition, purchase order or scheduling agreement.

MD11
Create Planned Order
This transaction is used to create a planned order. The initial screen requires the user to enter a planned order profile or reference another planned order. The next screen requires the user to enter the material, MRP area, and order quantity; the start and finish dates for the order can also be entered. The data can be saved and the transaction will display the planned order.

MD12
Change Planned Order
This transaction can be used to change a planned order. The initial screen requires the user to enter a planned order number. The user can then change the planned order quantity, start and finish dates, and the source of supply.

MD13
Display Planned Order
This transaction can be used to display a planned order. The initial screen requires the user to enter a planned order number. The user can then display the planned order quantity, start and finish dates, and the source of supply.

MD14
Convert Planned Order to Purchase Requisition
This transaction is used to convert an existing planned order to a purchase requisition. The initial screen requires the user to enter a planned order. The next screen allows the quantity to be changed; the plant, storage location, delivery date, release date, MRP controller, and purchasing group can also be changed. When the transaction is posted, a message will appear with the purchase requisition number.

MD15
Collective Conversion of Planned Order to Purchase Requisition
This transaction is used to convert a number of planned orders to purchase requisitions. The initial screen requires the user to enter a plant along with an MRP controller, a material or a WBS element. The next screen shows the relevant planned orders and the user can select the planned orders he or she wishes to convert to purchase requisitions.

MD16
Display Planned Orders
This transaction is used to display planned orders. The initial screen gives the user the choice to display planned orders, by MRP controller, material, production version, line from production version, or WBS element. The user can select one of the options and the transaction displays the relevant planned orders.

MD17
Collective Requirements Display
This transaction shows the collective requirements for a material. The initial screen requires the user to enter a material, plant and a production version. The transaction will show the collective requirements for the entered criteria. This transaction is mainly used in repetitive manufacturing.

MD20
Create Planning File Entry
This transaction is used to create a planning file entry for a single material. The transaction can be used when a new material that has not been in the MRP run can be added. The initial screen requires the user to enter a material, and the MRP area or plant. Users can then select which planning file entry they require and then press Enter. The transaction will display that the material has been marked for the MRP run.

MD21
Display Planning File Entries
This transaction is used to display planning file entries. The initial screen requires the user to enter a material and either a plant or an MRP area. Other selection data can be entered, such as a low-level code, re-explode BOM indicator, or the MPS item indicator. The output shows the planning file entries for the material.

MD25
Create Planning Calendar
This transaction is used to create a planning calendar. The initial screen requires the user to enter a plant and a planning calendar number. The next screen requires a description to be added for the planning calendar. The user can select the option for the transaction to calculate the periods and can select weeks, months, workdays, or years.

MD26
Change Planning Calendar
This transaction is used to change a planning calendar. The initial screen requires the user to enter a plant and a planning calendar number. The next screen allows the user to change the planning calendar description and the user can then change the existing periods of the planning calendar.

MD27
Display Planning Calendar
This transaction is used to display a planning calendar. The initial screen requires the user to enter a plant and a planning calendar number. The next screen shows the planning calendar header, and the user can then review the defined periods.

MD43
Single Item Planning – Interactive
This transaction is used to plan a single material. The initial screen requires the user to enter the material and plant. A number of selection values can be entered, such as the processing key, creation indicator for purchase requisitions, automatic schedule line indicator, and the planning mode indicator. The next screen shows the planning result for the material, and the user has the ability to execute the planning run or to reschedule, set firming dates, create a procurement proposal, or create a production order.

MD44
Evaluation of the Planning Situation
This transaction is used to evaluate a planning situation for a material. The initial screen requires the user to enter a material, plant and a layout for the MPS evaluation. The planning situation for the material is shown in the output screen: the warehouse stock, planned receipts, issues, available quantity and ATP quantity for the periods of the evaluation.

MD45
Evaluation of the Planning Result
This transaction is used to evaluate a planning result for a material. The initial screen requires the user to enter a material, plant and a layout for the MPS evaluation. The planning result for the material is shown in the output screen: the warehouse stock, planned receipts, issues, available quantity and ATP quantity for the periods of the evaluation.

MD46
Evaluation of the Planning Result for MRP Controller
This transaction is used to evaluate the planned result for a specific MRP controller. The initial screen requires the user to enter the MRP controller with either a MRP area or plant. It is possible to restrict the values by entering selection criteria, such as MRP date, processing date or stock coverage. The output shows the MRP list for materials associated with the MRP controller.

MD47
Evaluation of Product Group Planning
This transaction is used to evaluate a planning result for a product group. The initial screen requires the user to enter a product group, plant and a layout for the MPS evaluation. The planning result for the product group is shown in the output screen: the warehouse stock, planned receipts, issues, available quantity and ATP quantity for the periods of the evaluation.

MD48
Cross-Plant Evaluation
This transaction is used to evaluate a planning situation for a material across plants. The initial screen requires the user to enter a material and a layout for the MPS evaluation. The planning situation for the material is shown in the output screen: the warehouse stock, planned receipts, issues, available quantity and ATP quantity for the periods of the evaluation.

MD4C
Multi-level Order Report
This transaction is used to display the stock requirements for materials from a sales order, project, WBS element, planned order, production or process order. The initial screen shows a number of tabs where the user can enter a sales order, a WBS element, etc. After the user has entered in an order, the next screen shows the materials that are required by the order and the stock/requirements for the material.

MD50
Make-To-Order Planning – Multi-Level
This transaction is used to plan the details for a make-to-order sales order. The initial screen requires the user to enter the sales order and the sales order item number. This transaction generates the sales order specific requirement or planning only.

MD51
Project Planning – Multi-Level
This transaction is used to plan material requirement for a project or WBS element. The initial screen requires the user to enter a project or a WBS element; in addition, the user can enter a number of MRP control parameters.

MD61
Create Planned Independent Requirements
This transaction allows the user to create planned independent requirements for a material or product group. The initial screen requires a product group or a material to be entered, along with the MRP area, plant number and the planning horizon. The next screen lets the user enter independent requirement values into the planning table for the periods specified. After the values have been entered, the requirements can be saved.

MD62
Change Planned Independent Requirements
This transaction allows the user to change the planned independent requirements for a material or product group. The initial screen requires a product group or a material to be entered, along with the MRP area, plant number and the planning horizon. The next screen lets the user revise the independent requirement values into the planning table for the periods specified. After the necessary changes have been made, the requirements can be saved.

MD63
Display Planned Independent Requirements
This transaction allows the user to display the planned independent requirements for a material or product group. The initial screen requires a product group or a material to be entered, along with the MRP area, plant number and the planning horizon. The next screen lets the user review the independent requirement values into the planning table for the periods specified.

MD64
Standard Independent Requirements (Create)
This transaction allows the user to create standard independent requirements for a material or product group. The initial screen requires a product group or a material to be entered, along with the MRP area, plant number and the planning horizon. The next screen lets the user enter independent requirement values into the planning table for the periods specified. After the values have been entered, the requirements can be saved.

MD65
Change Standard Independent Requirements
This transaction allows the user to change the standard independent requirements for a material or product group. The initial screen requires a product group or a material to be entered, along with the MRP area, plant number and the planning horizon. The next screen lets the user revise the independent requirement values into the planning table for the periods specified. After the necessary changes have been made, the requirements can be saved.

MD66
Display Standard Independent Requirements
This transaction allows the user to display the standard independent requirements for a material or product group. The initial screen requires a product group or a material to be entered, along with the MRP area, plant number and the planning horizon. The next screen lets the user review the independent requirement values into the planning table for the periods specified.

MD73
Display Total Requirements
This transaction shows the total requirements for a material, requirements plan or an MRP controller. The initial screen requires the user to enter either a material, requirements plan or an MRP controller, along with a plant and a display option. The next screen shows the planned independent requirements with any assigned customer requirements for the upcoming periods.

MD74
Reorganizing Independent Requirements – Adjusting Requirements
This transaction is used when there is a need to reorganize existing independent requirements for a plant. The initial screen requires the user to enter a plant, material, requirement types, version, MRP area or key date. In addition, the user can set the Test Mode flag to stop unnecessary updates. The next screen shows the number of independent requirements that were selected and the number of requirements that are to be adjusted.

MD75
Independent Requirements Reorganization – Delete Old Requirements
This transaction is used when there is a need to reorganize existing independent requirements for a plant. The initial screen requires the user to enter a plant, material, requirement types, version, MRP area or key date. In addition, the user can set the Test Mode flag to stop unnecessary updates. The next screen shows the number of independent requirements that were selected and the number of requirements that are to be deleted.

MD76
Reorganizing Independent Requirements – Delete History
This transaction is used when there is a need to reorganize existing independent requirements for a plant and delete history records. The initial screen requires the user to enter a plant, material, requirement types, version, MRP area or key date. In addition, the user can set the Test Mode flag to stop unnecessary updates. The next screen shows the number of independent requirements that were selected and the number of history records that are to be deleted.

MD79
PP Demand Management – Microsoft Excel List Viewer
This transaction is used to display the demand requirements for the selection criteria and download to Microsoft Excel. The initial screen allows the user to enter a material number or a requirements plan in addition to the requirements type, plant, or requirements date. The transaction displays a pop-up screen, which offers the user a choice of processing mode: table or pivot table. The transaction will then download the information to an Excel spreadsheet.

MD81
Create Customer-Independent Requirements
This transaction is used to enter the customer requirement directly instead of using a sales order. The initial screen requires the user to enter the delivering plant; the user can optionally enter the delivery date and the requirements type. The next screen requires the user to enter the materials associated with the independent requirements as well as the total quantity. The transaction displays the customer-independent requirements number when the values are posted.

MD82
Change Customer-Independent Requirements
This transaction is used to change existing customer-independent requirements. The initial screen requires the user to enter a requirements plan number. The next screen shows the existing customer-independent requirements, and the user can change the value of the requirement, delete existing line items or create new customer-independent requirements.

MD83
Display Customer Independent Requirements
This transaction is used to display existing customer-independent requirement. The initial screen requires the user to enter a requirements plan number. The next screen shows the existing customer-independent requirements, and the user can review the line items in the customer-independent requirement.

MDL1
Create Production Lot
This transaction is used to create a production lot, which is a quantity of an assembly that is planned and produced together. The initial screen requires the user to enter a production lot number and a production lot profile. The next screen allows the user to enter a material number, and the production lot can be saved. The production lot number is a system generated WBS element.

MDL2
Change Production Lot
This transaction is used to change a production lot, which is a quantity of an assembly that is planned and produced together. The initial screen requires the user to enter a production lot number. The next screen allows the user to change the description of the production lot or material number.

MDL3
Display Production Lot
This transaction is used to display a production lot, which is a quantity of an assembly that is planned and produced together. The initial screen requires the user to enter a production lot number. The next screen allows the user to display the production lot details.

MDLD
Print MRP List
This transaction is used to print an existing MRP list. The initial screen allows the user to enter a single or range of plants, an MRP area, MRP controller, as well as selection criteria to reduce the output selection. The transaction will display a pop-up screen and will require the user to enter a printer number.

MDVP
Collective Availability Check
This transaction is used to perform a collective availability check on planned orders. The initial screen allows the user to enter selection criteria, such as planned order, production plant, MRP controller, production scheduler, and production version.

MF12
Display Document Log Information
This transaction is used to display document log information. The initial screen allows the user to enter selection criteria to reduce the number of document logs displayed. The selection criteria include plant, material, posting date, sales order, and production lot. The output shows the document logs for the selection criteria and the user can choose to select the log and review the log details.

MF26
Display Reporting Point Information
This transaction is used to display the confirmations for reporting point back flushing. The initial screen requires a plant to be entered, and selection criteria can also be entered such as material, MRP controller and production version. The output shows the reporting points per material. The user can select a reporting point and view the detailed information.

MF30
Creation of Preliminary Cost Estimates for Product Cost Collectors
This transaction is used to create preliminary cost estimates for product cost collectors. The initial screen requires the user to enter a costing date, plant and material. The transaction processes the information in the background and displays a message log, indicating if there is any warning or error messages. In addition the transaction will display the number of product cost collectors costed.

MF41
Document Specific Backflush Reversal
This transaction is used to reverse a backflush for a specific document. The initial screen requires the user to enter a reversal date, a reversal selection, such as make to stock, make to order, kanban or production lot, and other selection criteria. The transaction will display all the relevant documents based on the selection criteria. The user can then select the documents he or she requires and reverse the backflush.

MF42N
Collective Entry of Backflushes
This transaction is used to perform the backflushing of products. The transaction requires the user to enter the material and quantity of the items to be backflushed. The user can also enter a plant, planned order number, production version and a quantity of scrap if appropriate. When all the materials to be backflushed have been entered, they can be posted.

MF45
Post Process Backflush Items
This transaction is used to perform individual backflushing in repetitive manufacturing. The initial screen allows the user to enter a material, plant, production version, or a production line.

MF46
Collective Post Processing
This transaction is used to perform collective backflushing in repetitive manufacturing. The initial screen allows the user to enter the posting date and plant number. The next screen lets the user enter a number of materials, along with the relevant sales order information.

MF50
Change Planning Table
This transaction is used to change a planning table. The initial screen requires the user to enter a plant or MRP area along with a material, product group, production line, or MRP controller. The next screen allows the user to enter values for the capacity and the materials in the planning table.

MF51
Production List for Repetitive Manufacturing
This transaction is used to display production lists for repetitive manufacturing. The initial screen requires the user to enter a plant, examination period, and production line. The next screen shows the production list, which shows the production line, the total quantity, order number and end date.

MF52
Display Planning Table
This transaction is used to display a planning table. The initial screen requires the user to enter a plant or MRP area along with a material, product group, production line, or MRP controller. The next screen allows the user to review values for the capacity and the materials in the planning table.

MF57
Planning Table by MRP Lists
This transaction is used to display the planning table by MRP lists. The initial screen requires the user to enter the plant and MRP controller. A number of other selection criteria fields can be entered, such as MRP date, processing date or day’s supply. The next screen shows the materials associated with the planning table.

MF60
Material Staging – Pull List
This transaction is used to create the pull list for material staging; it can create stock transfer requirements to stage the materials to the production storage locations. The initial screen requires the user to enter a specific plant, the date for the requirements, as well as a number of selection criteria that can be entered to restrict the processing. The next screen shows the total requirements, and for each line item the user can enter the quantity staged or create replenishment proposals.

MF63
Material Staging Situation
This transaction is used to display the staging situation and post material to the production storage location. The initial screen requires the user to enter a specific plant, the date for the requirements, as well as a number of selection criteria that can be entered to restrict the processing. The output screen shows the requirements details and the missing quantities for the planned orders.

MF65
Stock Transfer for Reservation
This transaction is used to display and post the existing stock transfers for reservations. The initial screen has no mandatory fields, but the user can enter a range of selection criteria, such as material, plant, MRP controller, WBS element, or sales order. The next screen shows the material for the reservations that can be posted. The user can use batch determination if the material is batch managed, or the goods movements can be posted immediately.

MF68
Message Logs for Material Staging
This transaction is used to display the material staging message logs for a specific period. The initial screen allows the user to enter a date range and user names for the message logs. The next screen shows the message logs for the users entered within the date range.

MF70
Aggregate Collective Backflush
This transaction is used when a large volume of backflushing needs to be processed. The initial screen requires the user to enter the plant or plants for the backflushing, as well as the backflush processes to be carried out and the production type. By separating the backflush processes, the user can instruct the system to post the goods receipts, and reduce the production quantities and capacity requirements immediately. The partial or less critical functions can then be carried out at a later time.

MP30
Execute Material Forecast
This transaction is used to execute a forecast for a material. The forecast screen in the material master must be completed in order to execute a forecast. The initial screen requires the user to enter a material number and plant number. The next screen shows the forecast data from the material master and the user can then display the historical values or execute the forecast. A pop-up screen will offer periods that the user can select from. The transaction will then display the forecast for next twelve periods, which can then be saved.

MP31
Change Material Forecast
This transaction is used to change an existing material forecast. The initial screen requires the user to enter a material and a plant. The next screen shows the forecast details for the material, and the user can select to view the historical values or the forecast values. By selecting the forecast values, the user can then make changes to the forecast values for the material.

MP32
Display Material Forecast
This transaction is used to display an existing material forecast. The initial screen requires the user to enter a material and a plant. The next screen shows the forecast details for the material, and the user can select to view the historical values or the forecast values.

MP33
Forecast Reprocessing
This transaction is used to reprocess a forecast for a plant and an MRP controller. The user must enter a plant and an MRP controller on the initial screen. In addition, the user can select an error class to process, such as reorder level, model selection, initializations, etc. The next screen shows the materials that are available to be reprocessed. The user can select a material and the forecast can be reprocessed.

MP38
Execute Mass Forecast
This transaction allows the mass execution of forecasts for a plant or range of plants. The initial screen allows the user to enter the plant or plants, MRP areas, materials and ABC indicator. The transaction will show on the initial screen the number of plants and materials selected. The user can then choose to restrict the entries further or to execute the mass forecast. The output screen shows the information for the forecasts processed.

MP39
Material Forecast Printing
This transaction is used to print the materials forecasts for a specific plant. The initial screen requires the user to enter a plant number and period indicator. The transaction will generate a pop-up screen that will require that the user to enter a printer number. Subsequently, the transaction will indicate that the printing has been completed.

MP80
Forecast Profile Create
This transaction allows the creation of a forecast profile, which can be used in the material master record. The initial screen requires the user to enter a four-character profile number. The next screen requires a forty-character description; the user can select the fields the profile should contain, specifying whether each field is to be copied to the material master record as a fixed value or as a default value. The data screen allows the user to enter the fixed values for the fields selected.

MP81
Forecast Profile Change
This transaction allows the user to change a forecast profile, which can be used in the material master record. The initial screen requires a forecast profile to be entered. The user can then change the profile description and then add or change the values in the profile. If additional fields were selected to have a fixed value or as a default value, then the user must enter the fixed values for the fields selected.

MP82
Forecast Profile Delete
This transaction allows the user to delete a forecast profile, which was used in the material master record. The initial screen requires a forecast profile to be entered. The transaction will display a message to confirm that the forecast profile is to be deleted.

MP83
Forecast Profile Display
This transaction allows the user to display a forecast profile, which can be used in the material master record. The initial screen requires a forecast profile to be entered. The user can then display the profile description and review the values in the profile.

MS31
Create Planning Scenario
This transaction is used to create a planning scenario. The initial screen requires a three character planning scenario number and a forty-character description. The user can also define the default settings for the control parameters, such as long-term planning, gross long-term planning or short term simulation. The next screen allows the user to enter planning period, control parameters, gross requirements planning, receipts, or BOM explosion. The planning scenario can then be assigned to a planned independent requirement, and then the user can release and save the planning scenario.

MS32
Change Planning Scenario
This transaction is used to create a planning scenario. The initial screen requires the user to enter a planning scenario number. The following screen shows all the parameters that can be amended. The user can also change the assignment to a planned independent requirement.

MS33
Display Planning Scenario
This transaction is used to display a planning scenario. The initial screen requires the user to enter a planning scenario number. The following screen shows all the parameters that can be displayed. The user can also review the assignment of planned independent requirements.

MS44
Long-Term Planning Evaluation for Material
This transaction is used to create a long-term planning evaluation for a material based on a planning scenario. The initial screen requires the user to enter a planning scenario, material, plant and a layout. The user can also select an option to compare the evaluation with the planning situation or planning result. The output screen shows planning evaluation with the receipts, planned issues, available quantity and ATP quantity shown for the forecasted periods.

MSC1N
Create Batch
This transaction is used to create a batch for a material. The initial screen requires the user to enter the material number, batch number, plant, and storage location. The transaction takes the user to the first data screen, where the user can enter details on shelf life, expiration date, and trading data information. The user can also assign the batch to a class so that additional data can be added to characteristics describing the batch.

MSC2N
Change Batch
This transaction is used to change a batch for a material. The initial screen requires the user to enter the material number, batch number, plant, and storage location. The transaction takes the user to the first data screen, where the user can enter or change details on shelf life, expiration date, and trading data information. The user can also assign the batch to a class so that additional data can be added to characteristics describing the batch.

MSC3N
Display Batch
This transaction is used to display a batch for a material. The initial screen requires the user to enter the material number, batch number, plant, and storage location. The transaction takes the user to the first data screen, where the user can review details on shelf life, expiration date, and trading data information. The user can also review the classification information assigned to the batch.

MSC4N
Display Change Documents for Batch
This transaction is used to display changes that have been made to a specific material batch. The initial screen requires the user to enter the material number, batch number, plant, and storage location. The next screen shows the changes made to the batch, such as the data and time the changes were made, and what objects were changed. The screen also shows the old data and the new data of each of the fields that have been changed.

PK01
Create Control Cycle
This transaction is used to create a kanban control cycle. The initial screen requires the user to enter a material, plant, and a supply area. The next screen allows the user to enter the number of kanbans and the kanban quantity as well as the control cycle replenishment strategy. Once all the values are entered, the control cycle can be saved, and the transaction will display the control cycle number that has been created.

PK02
Change Control Cycle
This transaction is used to change a kanban control cycle. The initial screen requires the user to enter a material, plant, and a supply area. On the next screen, the user can then change the number of kanbans, the quantity, and add a new control cycle replenishment strategy.

PK03
Display Control Cycle
This transaction is used to display a kanban control cycle. The initial screen requires the user to enter a material, plant, and a supply area. On the next screen, the user can then display the number of kanbans, the quantity, and review the control cycle replenishment strategy.

PK03NR
Display Control Cycle
This transaction is similar to transaction PK03, but instead of accessing the control cycle using the material, plant, and a supply area, the user can directly enter the control cycle number on the initial screen. On the next screen, the user can then display the number of kanbans, the quantity, and review the control cycle replenishment strategy.

PK05
Maintain Supply Area
This transaction is used to maintain the supply areas for a plant. The initial screen requires the user to enter a plant. The next screen shows the user the production supply areas for the plant. The user can change the description of the production supply areas already configured; the user can also add a new production supply area or delete an existing production supply area.

PK05S
Quick Entry Supply to Production Area
This transaction allows the user to enter supply area information into the system. The initial screen requires the user to enter a plant number. The next screen shows the existing supply areas for the plant and the storage location they are assigned to. The user can enter the responsible party, the unloading point and supply area description for existing supply areas. The transaction allows the user to enter new supply areas for the plant and assign them to a storage location.

PK06
Display Supply Area
This transaction is used to display the supply areas for a plant. The initial screen requires the user to enter a plant. The next screen shows the user the production supply areas that have been created for the plant. The user can select a supply area and review detailed information about the supply area.

PK10
Kanban Board Status
This transaction allows the maintenance of the user authorization for the kanban table. The initial screen requires entry of either the demand view of the kanban board or the supply view. The next screen shows the users and the statuses that can be set by them. Additional changes can be made for each user, or new users can be added to this transaction.

PK11
Kanban Plant Overview
This transaction is used to display where the kanbans are in the plant. The initial screen requires the user to enter a plant number and an optional supply area. The output can be sorted by material or supply area. The next screen shows the overview of the control cycles at the plant, with the output showing the material, supply area, kanban quantities, and kanban containers.

PK12N
Kanban Board: Supply Source Overview
This transaction is used for monitoring and changing kanban status for the supply source. The initial screen requires the user to enter the plant and either the person responsible, vendor, issuing plant, or storage location. The transaction will graphically show the kanbans that are “in process” and those “in transit.” The user can trigger replenishment for a kanban if required.

PK13N
Kanban Board: Demand Source Overview
This transaction is used for monitoring and changing kanban status for the demand source. The initial screen requires the user to enter the plant and either the person responsible, vendor, issuing plant, or storage location. The transaction will graphically show the supply area, material and kanban quantity. The user can select kanbans and save them to full or to empty.

PK17
Collective Kanban Print
This transaction allows kanbans for a plant to be printed. The initial screen requires the user to enter a printer and a plant. The user can restrict the kanban to be printed by entering selection criteria, such as storage location, supply area, vendor, material, or kanban status. The output screen shows the supply areas and kanban that are relevant to the selection criteria entered. The user can select the kanban for the supply area he or she wishes to print or individual kanbans.

PK18
Control Cycle Evaluation
This transaction is used to evaluate the control cycles for a plant. The initial screen requires the user to enter a plant number. The user can restrict the kanban to be printed by entering selection criteria, such as storage location, supply area, vendor, material, or kanban status. The output shows the supply areas relevant to the selection criteria. By selecting a supply area, the relevant kanban are shown and the user can see their status, i.e. whether they are in wait, empty, or full status.

PK21
Manual Entry of a Kanban Signal
This transaction allows the user to manually trigger a kanban signal. The initial screen allows the user to enter a kanban identification number, a control cycle number and kanban number, or a plant, supply area and kanban number. Once the information is entered, the user can either allow the transaction to automatically assign the next status, or manually enter a status, for example: wait, empty, in transit, full, or in use.

PK22
Enter Quantity Signal
This transaction allows the entry of a quantity signal for a control cycle. The initial screen requires the user to enter either a control cycle, or a plant, material and supply area. The transaction also requires a withdrawal quantity to be entered that will be removed from the kanbans. In this transaction, only kanbans with a full or in use status can be used.

PK23
Create an Event-Driven Kanban
This transaction is used to create an event-driven kanban, which is where material is not continually provided and replenished at a supply area, but replenished only when specifically triggered. The initial screen requires the user to enter either a control cycle number, or a material, plant and supply area. The user can enter the quantity to be released as well as the delivery date and time.

PK23L
Delete Event-Driven Kanbans
This transaction is used to delete an event-driven kanban. The initial screen requires the user to enter a plant, as well as selection criteria such as supply area, vendor, person responsible, storage location, etc. The user also has the option to run the transaction as a simulation so that no database updates are made.

PK31
Kanban Correction
This transaction is used to correct a kanban. The initial screen requires the user to enter a plant, material and supply area. The next screen shows the relevant kanbans, and the user can select the appropriate kanban and correct the kanban status, actual quantity or batch number.

PK41
Kanban Backflush
This transaction is used to backflush kanbans. The initial screen requires the user to enter a control cycle number or a plant and material. The next screen shows the relevant kanbans, and the user can post the backflush. This will confirm either a goods receipt or goods issue posting.

PK50
Kanban Processing: Error Display
This transaction allows the user to display the error messages for a kanban at a specific plant. The initial screen requires the user to enter a plant and any relevant selection criteria. The output screen shows the errors for each of the control cycles. The user can select a specific error message and review a detailed message on the kanban or the error. The user has the option to select the error and transfer to transaction PK31.

PK52
Kanban Calculation: Display Error Log
This transaction is used to display error logs for any kanban calculations for a specific plant. The initial screen requires the user to enter a plant and selection criteria, such as supply area or storage location, if required. The next screen will display the kanban calculation error logs for the plant entered.

PKMC
Control Cycle Maintenance: Display
This transaction gives an overview of the control cycles at a plant. The selection part of the screen requires the user to enter a plant; the user also can enter the supply area, the person responsible, or the control cycle number. The screen shows the control cycles for the selection entered. The details for each line include the supply area, material, number of kanbans, kanban quantity, storage location, control cycle status, and control cycle category.