Wednesday 19 March 2014

SAP PP Interview Questions

Back flush - The item which is in back flush will issue components Automatically. It means, you don't need manually issue components.Use this method when there is no batch controlled item exist.

Manual Issue - The item which is in manual, you should issue components manually. It means, you need to manually issue components.Use this method when there is batch controlled item exist.

Saturday 15 March 2014

PP Interview Questions & Answers

Split planned order during MRP run by production version?

We have 2 production lines within one plant to produce the same  finished  product.  For  planning, we  put  the  planning quantity for finish product in Demand Management with a daily planning period and differentiated the production line with a production version. The problem occurs when we run MRP. The system automatically accumulates the requirement in a same day demand. Hence, we need to automatically split the planned order with a different production line. Since the lot size range is the same, is there a more efficient way as to how we can split the planned order?

If you want to split the planned order by percentage, you can use quota arrangement (meq1). If you want to split order by capacity, then you might want to use fixed lot size, and finite capacity with option “ changing
production version on error”.