Split planned order during MRP run by production version?
We have 2 production lines within one plant to produce the same finished product. For planning, we put the planning quantity for finish product in Demand Management with a daily planning period and differentiated the production line with a production version. The problem occurs when we run MRP. The system automatically accumulates the requirement in a same day demand. Hence, we need to automatically split the planned order with a different production line. Since the lot size range is the same, is there a more efficient way as to how we can split the planned order?
If you want to split the planned order by percentage, you can use quota arrangement (meq1). If you want to split order by capacity, then you might want to use fixed lot size, and finite capacity with option “ changing
production version on error”.