Saturday, 15 March 2014

PP Interview Questions & Answers

Split planned order during MRP run by production version?

We have 2 production lines within one plant to produce the same  finished  product.  For  planning, we  put  the  planning quantity for finish product in Demand Management with a daily planning period and differentiated the production line with a production version. The problem occurs when we run MRP. The system automatically accumulates the requirement in a same day demand. Hence, we need to automatically split the planned order with a different production line. Since the lot size range is the same, is there a more efficient way as to how we can split the planned order?

If you want to split the planned order by percentage, you can use quota arrangement (meq1). If you want to split order by capacity, then you might want to use fixed lot size, and finite capacity with option “ changing
production version on error”.

Friday, 23 August 2013

SAP Factory Calendar ?

  1. Factory calendar contain company specific dates such as alternate working Saturdays, Plant shutdown etc. 
  2. You can create your company factory calendar via transaction code 'SCAL'. 
  3. Assignment of the factory calendar by plant is done in transaction code 'SM30 - V_T001W'. 
  4. An example of a SAP application that uses the factory calendar is the SAP MRP modules. 
  5. Assuming that you have a specified an alternate working Saturday, MRP will postponed the planned orders to the next working day if it happened to falls on a non-working Saturday.